19154 W WELBY WAY 91335

Certificate Information: 19154 W WELBY WAY 91335

Application / Permit
24010-20000-04616
Plan Check / Job No.
B24VN22149
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW DETACHED 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c)-(d). SOLAR INSTALLATION REQUIRED TO MEET KW PER TITLE 24 PRIOR TO COFO.
Permit Issued
Issued on 9/15/2025
Issuing Office
Current Status
CofO Issued on 3/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2024 APPLICANT
Assigned to Plan Check Engineer 11/14/2024 VIVIAN LAO
Corrections Issued 11/19/2024 VIVIAN LAO
Quality Review Completed 11/20/2024 GARO TELMI
Applicant returned to address corrections 6/23/2025 VIVIAN LAO
Applicant returned to address corrections 8/5/2025 VIVIAN LAO
Plan Check Approved 8/26/2025 VIVIAN LAO
Issued 9/15/2025 APPLICANT
CofO in Progress 3/11/2026 ARUTYUN MADATYAN
Permit Finaled 3/13/2026 JOHN JANSON
CofO Issued 3/13/2026 JOHN JANSON
Permit Finaled 3/13/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/21/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 11/21/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/21/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/25/2024 LEE GUILBEAUX
Sewer availability Cleared 11/25/2024 LEE GUILBEAUX
ZI Cleared 11/25/2024 FIPE LEILUA
Construction near power lines Cleared 2/26/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Finley,, Lawrence Rufus; Lic. No.: C46606 1178 E 9TH ST      LONG BEACH, CA 90813

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/30/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 9/30/2025 Partial Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 10/9/2025 Approved ARUTYUN MADATYAN
Pre-Inspection 10/28/2025 Partial Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 12/22/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 12/22/2025 Corrections Issued ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Approved ARUTYUN MADATYAN
Gas Test 12/22/2025 Partial Inspection ARUTYUN MADATYAN
Green Building Rough 12/22/2025 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Rough 12/22/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 12/22/2025 Corrections Issued ARUTYUN MADATYAN
Sewer 12/22/2025 Not Ready for Inspection ARUTYUN MADATYAN
Underground Mechanical 12/22/2025 Not Ready for Inspection ARUTYUN MADATYAN
Verify Sprinkler Sign Off 12/22/2025 Not Ready for Inspection ARUTYUN MADATYAN
Wood Frame 12/22/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 1/12/2026 Conditional Approval ARUTYUN MADATYAN
ELECTRICAL-Rough 1/12/2026 Approved ARUTYUN MADATYAN
PLUMBING-Rough 1/12/2026 Not Ready for Inspection ARUTYUN MADATYAN
Sewer 1/12/2026 Approved ARUTYUN MADATYAN
Underground Mechanical 1/12/2026 Approved ARUTYUN MADATYAN
Insulation 1/14/2026 Approved ARUTYUN MADATYAN
PLUMBING-Rough 1/14/2026 Approved ARUTYUN MADATYAN
Green Building Rough 1/28/2026 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 1/28/2026 Partial Approval ARUTYUN MADATYAN
Shower Pan 1/28/2026 Approved ARUTYUN MADATYAN
Shower Pan 1/29/2026 Approved ARUTYUN MADATYAN
Drywall Nailing 2/4/2026 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 2/4/2026 Partial Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 3/3/2026 Approved ARUTYUN MADATYAN
Final 3/3/2026 Corrections Issued ARUTYUN MADATYAN
Green Building Final 3/3/2026 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 3/3/2026 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 3/3/2026 Not Ready for Inspection ARUTYUN MADATYAN
Smoke Detectors 3/3/2026 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 3/10/2026 Approved ARUTYUN MADATYAN
Final 3/10/2026 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 3/10/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 3/10/2026 Approved ARUTYUN MADATYAN
Service/Power Release 3/10/2026 Approved ARUTYUN MADATYAN