6447 N CLYBOURN AVE 91606

Certificate Information: 6447 N CLYBOURN AVE 91606

Application / Permit
24010-20000-04575
Plan Check / Job No.
B24VN21869
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached garage with addition to an ADU per Ordinance
Permit Issued
Issued on 1/6/2025
Issuing Office
Current Status
CofO Issued on 1/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2024 APPLICANT
Assigned to Plan Check Engineer 11/6/2024 ALEXANDER JOO
Corrections Issued 11/7/2024 ALEXANDER JOO
Applicant returned to address corrections 11/26/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 12/4/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 12/18/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 12/19/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 12/26/2024 CARLOS MONTES
Plan Check Approved 1/6/2025 CARLOS MONTES
Issued 1/6/2025 APPLICANT
CofO in Progress 12/12/2025 JOSE AVILA
Permit Finaled 1/2/2026 RUBEN SALAS
CofO Issued 1/2/2026 RUBEN SALAS
Permit Finaled 1/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/21/2024 EDGAR ALCARAZ
Construction within easement Cleared 11/21/2024 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 11/21/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 11/21/2024 EDGAR ALCARAZ
Sewer availability Cleared 11/21/2024 EDGAR ALCARAZ

Contact Information

Contractor Graceland Remodeling Inc; Lic. No.: 1061970-B       ,
Engineer Braun,, Jason; Lic. No.: C70948 14390 SHAWNEE ST      MOORPARK, CA 93021

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 1/10/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Pre-Inspection 1/10/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Underground Mechanical 1/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 1/14/2025 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 1/14/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 1/14/2025 Not Ready for Inspection JENNIFER RABUCHIN
Underground Mechanical 1/14/2025 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 1/17/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 1/23/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 2/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 2/4/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/4/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/7/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 2/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/11/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 2/11/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 2/11/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 2/14/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 2/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/19/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 2/19/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 2/19/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 2/19/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 2/24/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Final 3/12/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 3/12/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 3/12/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Final 3/12/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 3/12/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 3/12/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 3/12/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 3/19/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 3/19/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 3/19/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 3/19/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 3/19/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 3/19/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 3/19/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 4/14/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 4/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 4/14/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 4/14/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 4/14/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/14/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/14/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 12/11/2025 OK to Issue CofO JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV Approved JOSE AVILA