7525 N SEDAN AVE 91307
Certificate Information: 7525 N SEDAN AVE 91307
- Application / Permit
- 24010-20000-04555
- Plan Check / Job No.
- B24VN21547
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d)
- Permit Issued
- Issued on 6/18/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2024 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/10/2024 | NILOOFAR MEHRAIN |
| Quality Review Completed | 11/13/2024 | JASON HEALEY |
| Building Plans Picked Up | 11/27/2024 | APPLICANT |
| Applicant returned to address corrections | 2/20/2025 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 2/27/2025 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/4/2025 | NILOOFAR MEHRAIN |
| Issued | 6/18/2025 | APPLICANT |
| CofO in Progress | 12/17/2025 | JEFFREY HARTLINE |
| Permit Finaled | 12/27/2025 | MICHAEL PELHAM |
| CofO Issued | 12/27/2025 | MICHAEL PELHAM |
| Permit Finaled | 12/27/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 11/19/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 2/7/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 2/7/2025 | GEVORK KARAPETYAN |
| Hydrant and Access approval | Cleared | 2/13/2025 | FRANK GOMEZ |
Contact Information
| Contractor | Nasser Nima; Lic. No.: 1096564-B | 8057 DARBY PL RESEDA, CA 91335 |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/9/2025 | Partial Approval | JEFFREY HARTLINE |
| Excavation/Setback/Form/Re-Bar | 7/16/2025 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 7/16/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2025 | Partial Approval | JEFFREY HARTLINE |
| Deputy Wood Construction | 8/13/2025 | Conditional Approval | HENRY KIM |
| ELECTRICAL-Rough | 8/14/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 8/14/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 8/14/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 8/26/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 8/26/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 8/26/2025 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 8/26/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 9/3/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 9/3/2025 | Partial Approval | JEFFREY HARTLINE |
| Drywall Nailing | 9/10/2025 | Approved | JEFFREY HARTLINE |
| Shower Pan | 9/10/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 9/17/2025 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 10/3/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 12/9/2025 | Approved | JEFFREY HARTLINE |
| Final | 12/9/2025 | Corrections Issued | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 12/9/2025 | Approved | JEFFREY HARTLINE |
| Green Building Final | 12/9/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 12/9/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 12/9/2025 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 12/9/2025 | SGSOV Not Required | JEFFREY HARTLINE |
| Service/Power Release | 12/9/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 12/9/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 12/12/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 12/12/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 12/12/2025 | Approved | JEFFREY HARTLINE |
| Final | 12/17/2025 | OK to Issue CofO | JEFFREY HARTLINE |
| Service/Power Release | 12/17/2025 | Approved | JEFFREY HARTLINE |