7525 N SEDAN AVE 91307

Certificate Information: 7525 N SEDAN AVE 91307

Application / Permit
24010-20000-04555
Plan Check / Job No.
B24VN21547
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d)
Permit Issued
Issued on 6/18/2025
Issuing Office
Valley
Current Status
CofO Issued on 12/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2024 APPLICANT
Assigned to Plan Check Engineer 11/7/2024 NILOOFAR MEHRAIN
Corrections Issued 11/10/2024 NILOOFAR MEHRAIN
Quality Review Completed 11/13/2024 JASON HEALEY
Building Plans Picked Up 11/27/2024 APPLICANT
Applicant returned to address corrections 2/20/2025 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/27/2025 NILOOFAR MEHRAIN
Plan Check Approved 3/4/2025 NILOOFAR MEHRAIN
Issued 6/18/2025 APPLICANT
CofO in Progress 12/17/2025 JEFFREY HARTLINE
Permit Finaled 12/27/2025 MICHAEL PELHAM
CofO Issued 12/27/2025 MICHAEL PELHAM
Permit Finaled 12/27/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 11/19/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/19/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 11/19/2024 BIAINA HARITUNIAN
Sewer availability Cleared 11/19/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 2/7/2025 GEVORK KARAPETYAN
Construction within easement Cleared 2/7/2025 GEVORK KARAPETYAN
Hydrant and Access approval Cleared 2/13/2025 FRANK GOMEZ

Contact Information

Contractor Nasser Nima; Lic. No.: 1096564-B 8057 DARBY PL      RESEDA, CA 91335
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/9/2025 Partial Approval JEFFREY HARTLINE
Excavation/Setback/Form/Re-Bar 7/16/2025 Approved JEFFREY HARTLINE
Underground Mechanical 7/16/2025 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 7/25/2025 Partial Approval JEFFREY HARTLINE
Deputy Wood Construction 8/13/2025 Conditional Approval HENRY KIM
ELECTRICAL-Rough 8/14/2025 Approved JEFFREY HARTLINE
HVAC-Rough 8/14/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 8/14/2025 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 8/26/2025 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 8/26/2025 Approved JEFFREY HARTLINE
Green Building Rough 8/26/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 8/26/2025 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 8/26/2025 Approved JEFFREY HARTLINE
Insulation 9/3/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 9/3/2025 Partial Approval JEFFREY HARTLINE
Drywall Nailing 9/10/2025 Approved JEFFREY HARTLINE
Shower Pan 9/10/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 9/17/2025 Approved JEFFREY HARTLINE
Underground Mechanical 10/3/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 12/9/2025 Approved JEFFREY HARTLINE
Final 12/9/2025 Corrections Issued JEFFREY HARTLINE
Footing/Foundation/Slab 12/9/2025 Approved JEFFREY HARTLINE
Green Building Final 12/9/2025 Approved JEFFREY HARTLINE
HVAC-Final 12/9/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 12/9/2025 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Not Required JEFFREY HARTLINE
Service/Power Release 12/9/2025 Not Ready for Inspection JEFFREY HARTLINE
Smoke Detectors 12/9/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 12/12/2025 Approved JEFFREY HARTLINE
HVAC-Final 12/12/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 12/12/2025 Approved JEFFREY HARTLINE
Final 12/17/2025 OK to Issue CofO JEFFREY HARTLINE
Service/Power Release 12/17/2025 Approved JEFFREY HARTLINE