14079 W LA RUE ST 91340
Certificate Information: 14079 W LA RUE ST 91340
- Application / Permit
- 24010-20000-04542
- Plan Check / Job No.
- B24VN21436
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW DETACHED 2-STORY ADU Per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 5/15/2025
- Issuing Office
- Current Status
- CofO Issued on 4/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2024 | GEORGE JOLAKIAN |
| Corrections Issued | 11/21/2024 | GEORGE JOLAKIAN |
| Quality Review Completed | 11/21/2024 | RODOLFO ARIAS |
| Plan Check Approved | 5/15/2025 | GEORGE JOLAKIAN |
| Issued | 5/15/2025 | APPLICANT |
| CofO in Progress | 3/6/2026 | JENNIFER RABUCHIN |
| Permit Finaled | 4/7/2026 | RUBEN SALAS |
| CofO Issued | 4/7/2026 | RUBEN SALAS |
| Permit Finaled | 4/7/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/26/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 11/26/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/10/2024 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 4/23/2025 | RUEL COLE |
Contact Information
| Contractor | Ultimate Green Construction Inc; Lic. No.: 1023605-B | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/19/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/29/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 5/29/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Rough | 5/29/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/29/2025 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 5/29/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 5/30/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/11/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 6/11/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 6/11/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/2/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Deputy Wood Construction | 7/2/2025 | Conditional Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 7/2/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Rough | 7/2/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 7/2/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 7/2/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 7/2/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 7/9/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/9/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 7/9/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 7/9/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/9/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 7/9/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/18/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/18/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 7/18/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/18/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/18/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 7/18/2025 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 7/18/2025 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 7/18/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 7/24/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 7/29/2025 | Approved | JENNIFER RABUCHIN |
| Final | 11/7/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 11/7/2025 | Partial Approval | KEVIN BERBERYAN |
| Green Building Final | 11/7/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 11/7/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Service/Power Release | 11/7/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Smoke Detectors | 11/7/2025 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 11/12/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Final | 11/26/2025 | Approved | JENNIFER RABUCHIN |
| Final | 11/26/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/26/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 11/26/2025 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 11/26/2025 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 11/26/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/26/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 11/26/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 3/6/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 3/6/2026 | Approved | JENNIFER RABUCHIN |