323-325 W 52ND ST 90037

Certificate Information: 323-325 W 52ND ST 90037

Application / Permit
24010-20000-04475
Plan Check / Job No.
B24VN20877
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY (68' X 34' IRREGULAR SHAPE) DUPLEX WITH ATTACHED GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 3/18/2025
Issuing Office
Current Status
CofO Issued on 9/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 VAHAN JIVALAGIAN
Corrections Issued 11/2/2024 VAHAN JIVALAGIAN
Quality Review Completed 11/7/2024 OMID HEDAYAT
Applicant returned to address corrections 2/25/2025 VAHAN JIVALAGIAN
Plan Check Approved 3/7/2025 VAHAN JIVALAGIAN
Issued 3/18/2025 APPLICANT
CofO in Progress 9/18/2025 ALEJANDRO DE ARTOLA
Permit Finaled 9/21/2025 DEROLD HAUFF
CofO Issued 9/21/2025 DEROLD HAUFF
Permit Finaled 9/21/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/18/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 11/18/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 12/10/2024 DAVID LOPEZ
Sewer availability Cleared 12/10/2024 DAVID LOPEZ
Frnt yard landscape/Water mgmt Cleared 12/26/2024 DANIEL CORONADO
SB8 RUD Cleared 2/6/2025 BLAKE BOULIGNY
Hydrant and Access approval Cleared 2/13/2025 JERRY KAO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/9/2025 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/9/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/29/2025 Partial Approval MICHAEL LEWIS
Sewer 5/29/2025 Approved MICHAEL LEWIS
Wood Frame 5/29/2025 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/30/2025 Partial Approval ALEJANDRO DE ARTOLA
Insulation 5/30/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/9/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/18/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 7/18/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/21/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 7/21/2025 Approved ALEJANDRO DE ARTOLA
MERV13>=Rough 7/21/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/21/2025 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 7/21/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 7/23/2025 Approved ALEJANDRO DE ARTOLA
Insulation 7/23/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/31/2025 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 7/31/2025 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 8/4/2025 Corrections Issued ANTHONY RAMOS
Interior/Exterior Lathing 8/4/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 9/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 9/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 9/15/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/15/2025 Approved ALEJANDRO DE ARTOLA
Final 9/15/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 9/15/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 9/15/2025 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Final 9/15/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 9/15/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 9/15/2025 SGSOV Not Required ALEJANDRO DE ARTOLA
Service/Power Release 9/15/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 9/17/2025 Approved ALEJANDRO DE ARTOLA
Final 9/18/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
MERV13>=Final 9/18/2025 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 9/18/2025 Approved ALEJANDRO DE ARTOLA