20517 W GAULT ST 91306
Certificate Information: 20517 W GAULT ST 91306
- Application / Permit
- 24010-20000-04452
- Plan Check / Job No.
- B24VN20574
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- <ePLAN> NEW 25'0"X40'0" 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 2/7/2026
- Issuing Office
- Current Status
- Issued on 2/7/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2024 | MARVEL DELACRUZ |
| Corrections Issued | 11/5/2024 | MARVEL DELACRUZ |
| Quality Review Completed | 11/15/2024 | JASON HEALEY |
| Applicant returned to address corrections | 2/27/2025 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 4/22/2025 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 7/17/2025 | MARVEL DELACRUZ |
| Plan Check Approved | 1/29/2026 | MARVEL DELACRUZ |
| Issued | 2/7/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/2/2025 | BRYAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 4/2/2025 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2025 | BRYAN GODINEZ |
| Sewer availability | Cleared | 4/7/2025 | BRYAN GODINEZ |
| Construction near power lines | Cleared | 7/10/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 7/10/2025 | GEVORK KARAPETYAN |
| ZI | Cleared | 9/24/2025 | DAVID URITA |
| Hydrant and Access approval | Cleared | 1/14/2026 | KENNETH FRASER |
Contact Information
| Contractor | S & T Builders; Lic. No.: 1090121-B | , |
| Engineer | Hernandez,, Jose Antonio; Lic. No.: C69472 | 3557 E 58TH ST MAYWOOD, CA 90270 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/19/2026 | Corrections Issued | DAVID FASTIGGI |
| PLUMBING-Rough | 3/21/2026 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 3/21/2026 | Approved | ARUTYUN MADATYAN |
| Sewer | 3/21/2026 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 3/26/2026 | Approved | DAVID SCANTLIN |
| Deputy Wood Construction | 4/2/2026 | Conditional Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2026 | Approved | DAVID FASTIGGI |
| BUILDING-Rough-Frame | 4/16/2026 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Rough | 4/16/2026 | Approved | ALEXANDER HANDY |
| Green Building Rough | 4/16/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 4/16/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 4/16/2026 | Approved | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 4/16/2026 | Approved | ALEXANDER HANDY |
| Insulation | 4/21/2026 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 4/21/2026 | Partial Approval | ARUTYUN MADATYAN |
| Shower Pan | 4/21/2026 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 4/23/2026 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 4/23/2026 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 4/23/2026 | Partial Approval | ARUTYUN MADATYAN |
| Deputy Drilled-In Anchors | 5/4/2026 | Conditional Approval | ROBERT GOLD |