20517 W GAULT ST 91306

Certificate Information: 20517 W GAULT ST 91306

Application / Permit
24010-20000-04452
Plan Check / Job No.
B24VN20574
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
<ePLAN> NEW 25'0"X40'0" 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 2/7/2026
Issuing Office
Current Status
Issued on 2/7/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/22/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 MARVEL DELACRUZ
Corrections Issued 11/5/2024 MARVEL DELACRUZ
Quality Review Completed 11/15/2024 JASON HEALEY
Applicant returned to address corrections 2/27/2025 MARVEL DELACRUZ
Applicant returned to address corrections 4/22/2025 MARVEL DELACRUZ
Applicant returned to address corrections 7/17/2025 MARVEL DELACRUZ
Plan Check Approved 1/29/2026 MARVEL DELACRUZ
Issued 2/7/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/2/2025 BRYAN GODINEZ
Roof/Waste drainage to street Cleared 4/2/2025 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 4/7/2025 BRYAN GODINEZ
Sewer availability Cleared 4/7/2025 BRYAN GODINEZ
Construction near power lines Cleared 7/10/2025 GEVORK KARAPETYAN
Construction within easement Cleared 7/10/2025 GEVORK KARAPETYAN
ZI Cleared 9/24/2025 DAVID URITA
Hydrant and Access approval Cleared 1/14/2026 KENNETH FRASER

Contact Information

Contractor S & T Builders; Lic. No.: 1090121-B       ,
Engineer Hernandez,, Jose Antonio; Lic. No.: C69472 3557 E 58TH ST      MAYWOOD, CA 90270

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/19/2026 Corrections Issued DAVID FASTIGGI
PLUMBING-Rough 3/21/2026 Partial Approval ARUTYUN MADATYAN
Sewer 3/21/2026 Approved ARUTYUN MADATYAN
Sewer 3/21/2026 Off-Hour Fees Due
Footing/Foundation/Slab 3/26/2026 Approved DAVID SCANTLIN
Deputy Wood Construction 4/2/2026 Conditional Approval ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 4/3/2026 Approved DAVID FASTIGGI
BUILDING-Rough-Frame 4/16/2026 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 4/16/2026 Approved ALEXANDER HANDY
Green Building Rough 4/16/2026 Not Ready for Inspection ALEXANDER HANDY
HVAC-Rough 4/16/2026 Approved ALEXANDER HANDY
PLUMBING-Rough 4/16/2026 Approved ALEXANDER HANDY
Verify Sprinkler Sign Off 4/16/2026 Approved ALEXANDER HANDY
Insulation 4/21/2026 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 4/21/2026 Partial Approval ARUTYUN MADATYAN
Shower Pan 4/21/2026 Approved ARUTYUN MADATYAN
Drywall Nailing 4/23/2026 Approved ARUTYUN MADATYAN
Green Building Rough 4/23/2026 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 4/23/2026 Partial Approval ARUTYUN MADATYAN
Deputy Drilled-In Anchors 5/4/2026 Conditional Approval ROBERT GOLD