17211 W PRAIRIE ST 91325

Certificate Information: 17211 W PRAIRIE ST 91325

Application / Permit
24010-20000-04431
Plan Check / Job No.
B24VN20340
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) W/ ATTACHED TRELLIS **ePlan**
Permit Issued
Issued on 2/14/2025
Issuing Office
Current Status
CofO Issued on 2/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 NILOOFAR MEHRAIN
Corrections Issued 11/7/2024 NILOOFAR MEHRAIN
Quality Review Completed 11/15/2024 JASON HEALEY
Applicant returned to address corrections 1/27/2025 NILOOFAR MEHRAIN
Plan Check Approved 2/12/2025 NILOOFAR MEHRAIN
Issued 2/14/2025 APPLICANT
CofO in Progress 1/22/2026 CHRISTOPHER ROJAS
Permit Finaled 2/11/2026 RUBEN SALAS
Permit Finaled 2/11/2026 RUBEN SALAS
CofO Issued 2/11/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/5/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/5/2024 CARLOS AGUILERA
Street Frontage Cleared 12/5/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/6/2024 CARLOS AGUILERA
Sewer availability Cleared 12/6/2024 CARLOS AGUILERA
Grading Pre-Inspection Cleared 12/19/2024 CHARLES POWELL
Hydrant and Access approval Cleared 1/16/2025 JERRY KAO
GPI Written Notices Cleared 2/12/2025 NILOOFAR MEHRAIN

Contact Information

Contractor Southeast Home Builders Inc; Lic. No.: 1055627-B       ,
Engineer Kashe,, Andrew; Lic. No.: C94117 984 SILVERTIP DR      DIAMOND BAR, CA 91765

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/26/2025 Approved JAVIER RAMOS JR
Sewer 2/26/2025 Partial Approval JAVIER RAMOS JR
Sewer 3/19/2025 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 4/4/2025 Partial Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/4/2025 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 4/4/2025 Partial Inspection CHRISTOPHER ROJAS
Underground Mechanical 4/4/2025 Partial Inspection CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 4/8/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/8/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Special/Order Compliance 4/8/2025 Partial Inspection RAUL OLAGI
Excavation/Setback/Form/Re-Bar 4/21/2025 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/21/2025 Approved CHRISTOPHER ROJAS
Grounding or Bonding 4/21/2025 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/4/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/4/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 6/4/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 6/4/2025 Approved CHRISTOPHER ROJAS
Shower Pan 6/4/2025 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 6/4/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 6/16/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Insulation 6/16/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/16/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 7/16/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 12/16/2025 Corrections Issued CHRISTOPHER ROJAS
Final 12/16/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 12/16/2025 Approved CHRISTOPHER ROJAS
HVAC-Final 12/16/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Final 12/16/2025 Corrections Issued CHRISTOPHER ROJAS
Service/Power Release 12/16/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 12/16/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 1/21/2026 Approved CHRISTOPHER ROJAS
Final 1/21/2026 OK to Issue CofO CHRISTOPHER ROJAS
HVAC-Final 1/21/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Final 1/21/2026 Approved CHRISTOPHER ROJAS
Service/Power Release 1/21/2026 Approved CHRISTOPHER ROJAS
Smoke Detectors 1/21/2026 Approved CHRISTOPHER ROJAS