17411 W NORDHOFF ST 91325
Certificate Information: 17411 W NORDHOFF ST 91325
- Application / Permit
- 24010-20000-04395
- Plan Check / Job No.
- B24VN19029
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Proposed Detached Accessory Dwelling Unit per state law Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g) Type VB construction Sprinklered NFPA-13D THROUGH OUT
- Permit Issued
- Issued on 5/28/2025
- Issuing Office
- Current Status
- Issued on 5/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2024 | JAD BASMA |
| Corrections Issued | 10/19/2024 | JAD BASMA |
| Quality Review Completed | 10/25/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 12/11/2024 | JAD BASMA |
| Plan Check Approved | 2/26/2025 | JAD BASMA |
| Issued | 5/28/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/24/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 10/24/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2024 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 10/29/2024 | SARAH YOUSSEF |
| Sewer availability | Cleared | 10/29/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 10/30/2024 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 11/15/2024 | YINGSHI HUANG |
Contact Information
| Architect | Stockton,, Richard Kenneth; Lic. No.: NA35492 | , |
| Contractor | Tamam A Construction Inc; Lic. No.: 1003075-B | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Interior/Exterior Lathing | 6/16/2026 |
| Drywall Nailing | 6/16/2026 |
Inspection Request History
| Pre-Inspection | 3/24/2026 | Partial Inspection | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 3/31/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Underground Mechanical | 3/31/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 4/13/2026 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2026 | Corrections Issued | KEVIN BERBERYAN |
| Deputy Wood Construction | 5/20/2026 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 5/26/2026 | Corrections Issued | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2026 | Partial Approval | KEVIN BERBERYAN |
| HVAC-Rough | 5/26/2026 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 5/26/2026 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 6/8/2026 | Approved | KEVIN BERBERYAN |
| Sewer | 6/8/2026 | Approved | KEVIN BERBERYAN |
| Shower Pan | 6/8/2026 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/11/2026 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 6/11/2026 | Approved | KEVIN BERBERYAN |
| Insulation | 6/11/2026 | Approved | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 6/11/2026 | Approved | KEVIN BERBERYAN |