13874 W OSBORNE ST 91331

Certificate Information: 13874 W OSBORNE ST 91331

Application / Permit
24010-20000-04392
Plan Check / Job No.
B24VN20139
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached garage to new ADU PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 3/24/2025
Issuing Office
Current Status
CofO Issued on 6/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2024 APPLICANT
Assigned to Plan Check Engineer 10/24/2024 PINANK PATEL
Corrections Issued 10/25/2024 PINANK PATEL
Applicant returned to address corrections 2/25/2025 PINANK PATEL
Applicant returned to address corrections 2/26/2025 PINANK PATEL
Applicant returned to address corrections 3/10/2025 PINANK PATEL
Plan Check Approved 3/20/2025 NAREG ATARIAN
Issued 3/24/2025 APPLICANT
CofO in Progress 5/6/2026 OGANES TARAKHCHYAN
CofO Issued 6/4/2026 RUBEN SALAS
Permit Finaled 6/4/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/31/2024 CARLOS AGUILERA
Address approval Cleared 1/16/2025 RYAN CASTRO
Sewer availability Cleared 1/16/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/21/2025 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 5/28/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/11/2025 Partial Approval VINCENT HANLEY
Green Building Rough 7/11/2025 Not Ready for Inspection VINCENT HANLEY
Rough-Elec/Plmb/HVAC 7/11/2025 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 7/29/2025 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 7/29/2025 Partial Approval VINCENT HANLEY
Green Building Rough 7/29/2025 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 7/29/2025 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 7/29/2025 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 8/14/2025 Corrections Issued VINCENT HANLEY
Green Building Rough 8/14/2025 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 8/14/2025 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 8/20/2025 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 8/20/2025 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 9/2/2025 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 9/2/2025 Approved VINCENT HANLEY
HVAC-Rough 9/2/2025 Approved VINCENT HANLEY
PLUMBING-Rough 9/2/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/5/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/5/2025 Approved VINCENT HANLEY
Green Building Rough 9/5/2025 Approved VINCENT HANLEY
Insulation 9/5/2025 Approved VINCENT HANLEY
Drywall Nailing 9/19/2025 Approved VINCENT HANLEY
Service/Power Release 10/14/2025 Corrections Issued MATTHEW NELSON
Gas Test 10/27/2025 Corrections Issued VINCENT HANLEY
Underground Mechanical 10/27/2025 Corrections Issued VINCENT HANLEY
Gas Test 11/3/2025 Approved VINCENT HANLEY
Sewer 11/3/2025 Approved VINCENT HANLEY
Underground Mechanical 11/3/2025 Approved VINCENT HANLEY
Final 11/19/2025 Not Ready for Inspection MATTHEW NELSON
Green Building Final 11/19/2025 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 11/19/2025 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 11/19/2025 Approved MATTHEW NELSON
Final 12/5/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 12/5/2025 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/5/2025 SGSOV Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 4/22/2026 Not Ready for Inspection DAVID MATSON
Final 4/22/2026 Not Ready for Inspection DAVID MATSON
Green Building Final 4/22/2026 Approved DAVID MATSON
HVAC-Final 4/22/2026 Approved DAVID MATSON
PLUMBING-Final 4/22/2026 Approved DAVID MATSON
Service/Power Release 4/22/2026 Not Ready for Inspection DAVID MATSON
Final 4/27/2026 OK to Issue CofO OGANES TARAKHCHYAN
Service/Power Release 4/27/2026 Approved OGANES TARAKHCHYAN