9302 N TAMARACK AVE 91352

Certificate Information: 9302 N TAMARACK AVE 91352

Application / Permit
24010-20000-04382
Plan Check / Job No.
B24VN20036
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) one story ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 2/7/2025
Issuing Office
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 GEORGE JOLAKIAN
Corrections Issued 11/7/2024 GEORGE JOLAKIAN
Quality Review Completed 11/8/2024 RODOLFO ARIAS
Plan Check Approved 2/4/2025 GEORGE JOLAKIAN
Issued 2/7/2025 APPLICANT
CofO in Progress 9/3/2025 MATTHEW NELSON
Permit Finaled 11/13/2025 RUBEN SALAS
CofO Issued 11/13/2025 RUBEN SALAS
Permit Finaled 11/13/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/13/2024 BIAINA HARITUNIAN
Clean Up Green Up Cleared 11/13/2024 ASHLEY RODARTE
Eng Process Fee Ord 176,300 Cleared 11/13/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 11/13/2024 BIAINA HARITUNIAN
Sewer availability Cleared 11/13/2024 BIAINA HARITUNIAN
Certificate of Compliance Cleared 11/14/2024 ASHLEY RODARTE

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/12/2025 Partial Approval MATTHEW NELSON
Sewer 2/12/2025 Approved MATTHEW NELSON
Underground Mechanical 2/12/2025 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 2/27/2025 Approved MATTHEW NELSON
Deputy Wood Construction 4/2/2025 Conditional Approval JUAN VALENZUELA
Rough-Elec/Plmb/HVAC 4/9/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/23/2025 Conditional Approval DAVID MATSON
Green Building Rough 4/23/2025 Approved DAVID MATSON
Verify Sprinkler Sign Off 4/23/2025 Corrections Issued DAVID MATSON
Pre-Inspection 7/1/2025 Approved MATTHEW NELSON
Insulation 7/3/2025 Approved MATTHEW NELSON
Drywall Nailing 7/8/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 8/28/2025 Approved MATTHEW NELSON
Final 8/28/2025 Corrections Issued MATTHEW NELSON
Green Building Final 8/28/2025 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 8/28/2025 SGSOV Not Required MATTHEW NELSON
Service/Power Release 8/28/2025 Corrections Issued MATTHEW NELSON
Smoke Detectors 8/28/2025 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 8/28/2025 Approved MATTHEW NELSON
Final 9/2/2025 OK to Issue CofO MATTHEW NELSON
Service/Power Release 9/2/2025 Approved MATTHEW NELSON