12249 W ADDISON ST 91607

Certificate Information: 12249 W ADDISON ST 91607

Application / Permit
24010-20000-04347
Plan Check / Job No.
B24VN19812
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW DETACHED ADU PER STATE LAW NFPA 13D FIRE SPRINKLER THROUGH OUT
Permit Issued
Issued on 3/18/2025
Issuing Office
Current Status
CofO Issued on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2024 APPLICANT
Assigned to Plan Check Engineer 10/22/2024 JOSEPH RAFOLS
Corrections Issued 10/23/2024 JOSEPH RAFOLS
Applicant returned to address corrections 11/21/2024 ALEXANDER JOO
Applicant returned to address corrections 12/7/2024 ALEXANDER JOO
Applicant returned to address corrections 12/19/2024 ALEXANDER JOO
Plan Check Approved 1/30/2025 EDWIN MARTINEZ
Issued 3/18/2025 APPLICANT
CofO Issued 3/26/2026 RUBEN SALAS
Permit Finaled 3/26/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/4/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 11/4/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 11/6/2024 EDGAR ALCARAZ
Sewer availability Cleared 11/6/2024 EDGAR ALCARAZ
Miscellaneous Cleared 12/6/2024 JOANNA MARROQUIN
Specific Plan Cleared 12/6/2024 JOANNA MARROQUIN
Construction near power lines Cleared 1/28/2025 GEVORK KARAPETYAN

Contact Information

Contractor Susan Development And Construction Inc; Lic. No.: 1089492-B       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/24/2025 Approved RYAN SALAZAR
PLUMBING-Rough 4/24/2025 Partial Approval RYAN SALAZAR
Sewer 5/9/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 5/9/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 7/18/2025 Approved OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 7/18/2025 Approved OGANES TARAKHCHYAN
Shower Pan 7/18/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/28/2025 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 7/28/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/28/2025 Partial Approval OGANES TARAKHCHYAN
Insulation 8/1/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/1/2025 Approved OGANES TARAKHCHYAN
Drywall Nailing 8/7/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 2/19/2026 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 2/19/2026 Approved OGANES TARAKHCHYAN
Final 2/19/2026 Partial Approval OGANES TARAKHCHYAN
Green Building Final 2/19/2026 Approved OGANES TARAKHCHYAN
HVAC-Final 2/19/2026 Approved OGANES TARAKHCHYAN
PLUMBING-Final 2/19/2026 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 2/19/2026 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 2/19/2026 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 2/19/2026 Approved OGANES TARAKHCHYAN