741 E 94TH ST 90002
Certificate Information: 741 E 94TH ST 90002
- Application / Permit
- 24010-20000-04328
- Plan Check / Job No.
- B24VN19685
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePlan.* New detached two-story ADU at rear of lot. ADU per LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 2/10/2025
- Issuing Office
- Current Status
- Issued on 2/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2024 | HUAN LE |
| Corrections Issued | 12/13/2024 | HUAN LE |
| Quality Review Completed | 12/20/2024 | PRANITA SHAH |
| Plan Check Approved | 2/7/2025 | HUAN LE |
| Issued | 2/10/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/30/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 12/30/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2025 | JUSTIN BICOL |
| Sewer availability | Cleared | 1/13/2025 | JUSTIN BICOL |
Contact Information
| Contractor | Forty General Building Inc; Lic. No.: 1064226-B | , |
| Engineer | Manlangit,, Vicente; Lic. No.: NA75499 | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/19/2025 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 2/21/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Underground Mechanical | 2/21/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 2/25/2025 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 2/25/2025 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/26/2025 | Conditional Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/9/2025 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 7/9/2025 | Approved | JOHN KLARIN |
| Green Building Rough | 7/9/2025 | Approved | JOHN KLARIN |
| HVAC-Rough | 7/9/2025 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/9/2025 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 7/9/2025 | Approved | JOHN KLARIN |
| Insulation | 7/11/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/11/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 7/23/2025 | Approved | JOHN KLARIN |
| Shower Pan | 7/23/2025 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 9/8/2025 | Partial Inspection | ANTHONY EGSON |
| Final | 10/28/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 10/28/2025 | Approved | ANTHONY EGSON |
| Green Building Final | 10/28/2025 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/28/2025 | SGSOV Not Ready | ANTHONY EGSON |
| Service/Power Release | 10/28/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 10/28/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Special/Order Compliance | 2/4/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 5/4/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 5/4/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Final | 5/4/2026 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 5/4/2026 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 5/4/2026 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 5/4/2026 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 5/4/2026 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 5/4/2026 | Not Ready for Inspection | BEN MOLSTAD |