5918 N HINTON AVE 91367

Certificate Information: 5918 N HINTON AVE 91367

Application / Permit
24010-20000-04327
Plan Check / Job No.
B24VN19671
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN* NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) - PER ENGINEER
Permit Issued
Issued on 1/8/2025
Issuing Office
Current Status
CofO Issued on 8/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2024 APPLICANT
Assigned to Plan Check Engineer 10/18/2024 DANIEL ABRAMYAN
Corrections Issued 10/21/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 11/6/2024 ISIS ARGUETA
Plan Check Approved 11/13/2024 KAVIAN REFAHI
Issued 1/8/2025 APPLICANT
CofO in Progress 8/4/2025 TROY SANDERS
Permit Finaled 8/19/2025 JOHN JANSON
CofO Issued 8/19/2025 JOHN JANSON
Permit Finaled 8/19/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/22/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 10/22/2024 EDGAR ALCARAZ
Grading Pre-Inspection Cleared 10/30/2024 CHARLES POWELL
Sewer availability Cleared 10/31/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/1/2024 EDGAR ALCARAZ

Contact Information

Contractor R & Y Building Inc; Lic. No.: 1076518-B       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/13/2025 Approved GEVORK IPCHYAN
PLUMBING-Rough 2/19/2025 Partial Approval TROY SANDERS
Sewer 2/19/2025 Partial Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 3/4/2025 Approved TROY SANDERS
Footing/Foundation/Slab 3/4/2025 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Approved TROY SANDERS
Verify Sprinkler Sign Off 4/3/2025 Approved TROY SANDERS
ELECTRICAL-Rough 4/30/2025 Approved TROY SANDERS
PLUMBING-Rough 4/30/2025 Approved TROY SANDERS
Interior/Exterior Lathing 5/16/2025 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 6/3/2025 Approved TROY SANDERS
Green Building Rough 6/3/2025 Approved TROY SANDERS
HVAC-Rough 6/3/2025 Approved TROY SANDERS
Insulation 6/3/2025 Not Ready for Inspection TROY SANDERS
Insulation 6/5/2025 Approved TROY SANDERS
Drywall Nailing 6/10/2025 Not Ready for Inspection HENRY KIM
Drywall Nailing 6/12/2025 Approved SEAN WIRCH
Interior/Exterior Lathing 6/27/2025 Partial Approval TROY SANDERS
Shower Pan 6/27/2025 Approved TROY SANDERS
ELECTRICAL-Final 7/18/2025 Approved TROY SANDERS
Final 7/18/2025 Not Ready for Inspection TROY SANDERS
HVAC-Final 7/18/2025 Not Ready for Inspection TROY SANDERS
PLUMBING-Final 7/18/2025 Not Ready for Inspection TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/18/2025 SGSOV Approved TROY SANDERS
Service/Power Release 7/18/2025 Approved TROY SANDERS
Smoke Detectors 7/18/2025 Approved TROY SANDERS
ELECTRICAL-Final 7/25/2025 Approved GEVORK IPCHYAN
Final 7/25/2025 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Final 7/25/2025 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Final 7/25/2025 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Final 7/31/2025 Approved TROY SANDERS
Final 7/31/2025 OK to Issue CofO TROY SANDERS
HVAC-Final 7/31/2025 Approved TROY SANDERS
PLUMBING-Final 7/31/2025 Approved TROY SANDERS
Service/Power Release 8/18/2025 Approved TROY SANDERS