13709 W CHASE ST 91331

Certificate Information: 13709 W CHASE ST 91331

Application / Permit
24010-20000-04291
Plan Check / Job No.
B24VN19444
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY (23'-1" X 36'-5") SINGLE FAMILY DWELLING PER SB9 TWO-UNIT Development Ca Govt Code 65852.21- NFPA13D FIRE SPRINKLERS REQUIRED.
Permit Issued
Issued on 4/23/2025
Issuing Office
Valley
Current Status
CofO Issued on 4/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2024 APPLICANT
Assigned to Plan Check Engineer 10/24/2024 EDWARD MEHRABIAN
Corrections Issued 10/28/2024 EDWARD MEHRABIAN
Quality Review Completed 11/1/2024 OMID HEDAYAT
Building Plans Picked Up 11/6/2024 APPLICANT
Plan Check Approved 4/15/2025 EDWARD MEHRABIAN
Issued 4/23/2025 APPLICANT
CofO in Progress 2/6/2026 VINCENT HANLEY
Permit Finaled 4/10/2026 RUBEN SALAS
CofO Issued 4/10/2026 RUBEN SALAS
Permit Finaled 4/10/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/29/2024 RYAN CASTRO
Address approval Cleared 10/30/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/30/2024 RYAN CASTRO
Senate Bill 9 Cleared 10/31/2024 ALEX VELA
Sewer availability Cleared 11/6/2024 RYAN CASTRO
Hydrant and Access approval Cleared 4/3/2025 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Papazyan,, Andranik; Lic. No.: C56824 1015 VISTA GRANDE ST      BURBANK, CA 91501

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Final 5/5/2025 Partial Approval VINCENT HANLEY
Underground Mechanical 5/5/2025 Corrections Issued VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 5/15/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 5/15/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 6/18/2025 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/18/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/12/2025 Not Ready for Inspection KEVIN BERBERYAN
Green Building Rough 8/12/2025 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Rough 8/12/2025 Partial Approval KEVIN BERBERYAN
Verify Sprinkler Sign Off 8/12/2025 Not Ready for Inspection KEVIN BERBERYAN
Deputy Wood Construction 8/18/2025 Conditional Approval DAVID MATSON
Interior/Exterior Lathing 8/19/2025 Approved MICHAEL CORTEZ
Shower Pan 8/19/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Rough 8/26/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/2/2025 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Approved VINCENT HANLEY
Green Building Rough 9/2/2025 Approved VINCENT HANLEY
HVAC-Rough 9/2/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/5/2025 Approved VINCENT HANLEY
Insulation 9/5/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 9/5/2025 Approved VINCENT HANLEY
Drywall Nailing 9/12/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 11/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 11/14/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/24/2025 SGSOV Not Ready OGANES TARAKHCHYAN
Final 11/26/2025 Corrections Issued DAVID MATSON
Final 12/9/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 12/9/2025 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 12/9/2025 Approved OGANES TARAKHCHYAN
Final 12/22/2025 Corrections Issued VINCENT HANLEY
Green Building Final 12/22/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 12/22/2025 SGSOV Not Required VINCENT HANLEY
Service/Power Release 12/22/2025 Approved VINCENT HANLEY
Final 2/3/2026 OK to Issue CofO VINCENT HANLEY
HVAC-Final 2/3/2026 Approved VINCENT HANLEY
PLUMBING-Final 2/3/2026 Approved VINCENT HANLEY