13709 W CHASE ST 91331
Certificate Information: 13709 W CHASE ST 91331
- Application / Permit
- 24010-20000-04291
- Plan Check / Job No.
- B24VN19444
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY (23'-1" X 36'-5") SINGLE FAMILY DWELLING PER SB9 TWO-UNIT Development Ca Govt Code 65852.21- NFPA13D FIRE SPRINKLERS REQUIRED.
- Permit Issued
- Issued on 4/23/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2024 | EDWARD MEHRABIAN |
| Corrections Issued | 10/28/2024 | EDWARD MEHRABIAN |
| Quality Review Completed | 11/1/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 11/6/2024 | APPLICANT |
| Plan Check Approved | 4/15/2025 | EDWARD MEHRABIAN |
| Issued | 4/23/2025 | APPLICANT |
| CofO in Progress | 2/6/2026 | VINCENT HANLEY |
| Permit Finaled | 4/10/2026 | RUBEN SALAS |
| CofO Issued | 4/10/2026 | RUBEN SALAS |
| Permit Finaled | 4/10/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/29/2024 | RYAN CASTRO |
| Address approval | Cleared | 10/30/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2024 | RYAN CASTRO |
| Senate Bill 9 | Cleared | 10/31/2024 | ALEX VELA |
| Sewer availability | Cleared | 11/6/2024 | RYAN CASTRO |
| Hydrant and Access approval | Cleared | 4/3/2025 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 1015 VISTA GRANDE ST BURBANK, CA 91501 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Final | 5/5/2025 | Partial Approval | VINCENT HANLEY |
| Underground Mechanical | 5/5/2025 | Corrections Issued | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/15/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/15/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/18/2025 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Rough | 8/12/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 8/12/2025 | Partial Approval | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 8/12/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Deputy Wood Construction | 8/18/2025 | Conditional Approval | DAVID MATSON |
| Interior/Exterior Lathing | 8/19/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 8/19/2025 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Rough | 8/26/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 9/2/2025 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 9/2/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 9/2/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 9/5/2025 | Approved | VINCENT HANLEY |
| Insulation | 9/5/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 9/5/2025 | Approved | VINCENT HANLEY |
| Drywall Nailing | 9/12/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 11/12/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 11/14/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/24/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 11/26/2025 | Corrections Issued | DAVID MATSON |
| Final | 12/9/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 12/9/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/9/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 12/9/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 12/22/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 12/22/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 12/22/2025 | SGSOV Not Required | VINCENT HANLEY |
| Service/Power Release | 12/22/2025 | Approved | VINCENT HANLEY |
| Final | 2/3/2026 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 2/3/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 2/3/2026 | Approved | VINCENT HANLEY |