11037 N DE FOE AVE 91331
Certificate Information: 11037 N DE FOE AVE 91331
- Application / Permit
- 24010-20000-04278
- Plan Check / Job No.
- B24VN19340
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRREGULAR SHAPED ALL ELECTRIC ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1).
- Permit Issued
- Issued on 2/11/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 10/16/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 10/17/2024 | APPLICANT |
| Applicant returned to address corrections | 1/31/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 2/5/2025 | GIOVANNY CHAVEZ |
| Issued | 2/11/2025 | APPLICANT |
| CofO in Progress | 11/19/2025 | MICHEL ABAJAN |
| Permit Finaled | 12/2/2025 | RUBEN SALAS |
| CofO Issued | 12/2/2025 | RUBEN SALAS |
| Permit Finaled | 12/2/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/20/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 10/20/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 10/20/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/22/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 2310 W MAGNOLIA BLVD STE A BURBANK, CA 91506 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/9/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 5/15/2025 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/9/2025 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 6/9/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 6/9/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 6/11/2025 | Approved | RAUL OLAGI |
| HVAC-Rough | 6/11/2025 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/16/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 6/16/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 6/16/2025 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 6/16/2025 | Approved | MICHEL ABAJAN |
| Insulation | 6/24/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/24/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/1/2025 | Approved | MICHEL ABAJAN |
| Shower Pan | 7/8/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/18/2025 | Approved | MICHEL ABAJAN |
| Final | 11/18/2025 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 11/18/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 11/18/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 11/18/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2025 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 11/18/2025 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 11/18/2025 | Approved | MICHEL ABAJAN |