8113 N WOODMAN AVE 91402

Certificate Information: 8113 N WOODMAN AVE 91402

Application / Permit
24010-20000-04276
Plan Check / Job No.
B24VN19258
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ALL ELECTRIC DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 10/23/2024
Issuing Office
Current Status
CofO in Progress on 3/18/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/9/2024 APPLICANT
Assigned to Plan Check Engineer 10/17/2024 JEROME MAGAT PALMA
Corrections Issued 10/19/2024 JEROME MAGAT PALMA
Building Plans Picked Up 10/21/2024 APPLICANT
Issued 10/23/2024 APPLICANT
CofO in Progress 3/18/2026 VINCENT HANLEY

Permit Application Clearance Information

Address approval Cleared 10/21/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/21/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/21/2024 LEE GUILBEAUX
Sewer availability Cleared 10/21/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/21/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/25/2024 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 12/2/2024 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 12/2/2024 Not Ready for Inspection GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 12/5/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 12/5/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 1/9/2025 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 1/9/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/9/2025 Approved VINCENT HANLEY
Green Building Rough 1/9/2025 Approved VINCENT HANLEY
HVAC-Rough 1/9/2025 Approved VINCENT HANLEY
PLUMBING-Rough 1/9/2025 Approved VINCENT HANLEY
Insulation 1/15/2025 Corrections Issued MICHAEL CORTEZ
Interior/Exterior Lathing 1/15/2025 Partial Approval MICHAEL CORTEZ
Insulation 1/23/2025 Corrections Issued LOUIS ESCOTO
Drywall Nailing 1/30/2025 Approved VINCENT HANLEY
Insulation 1/30/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/4/2025 Approved LOUIS ESCOTO
Shower Pan 3/4/2025 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 5/15/2025 No Access for Inspection VINCENT HANLEY
Green Building Final 5/15/2025 No Access for Inspection VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/15/2025 SGSOV Not Required VINCENT HANLEY
Service/Power Release 5/15/2025 No Access for Inspection VINCENT HANLEY
Smoke Detectors 5/15/2025 No Access for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 5/15/2025 No Access for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 5/16/2025 Partial Approval VINCENT HANLEY
ELECTRICAL-Final 5/16/2025 Approved VINCENT HANLEY
Final 5/16/2025 Not Ready for Inspection VINCENT HANLEY
HVAC-Final 5/16/2025 Approved VINCENT HANLEY
PLUMBING-Final 5/16/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/16/2025 SGSOV Not Required VINCENT HANLEY
Smoke Detectors 5/16/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 6/10/2025 Partial Approval VINCENT HANLEY
Final 6/10/2025 Corrections Issued VINCENT HANLEY
Green Building Final 6/10/2025 Approved VINCENT HANLEY
Service/Power Release 6/10/2025 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 6/10/2025 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 3/17/2026 Approved VINCENT HANLEY
Final 3/17/2026 OK to Issue CofO VINCENT HANLEY