5725 1/2 N BERTRAND AVE 91316
Certificate Information: 5725 1/2 N BERTRAND AVE 91316
- Application / Permit
- 24010-20000-04266
- Plan Check / Job No.
- B24VN19177
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW DETACHED 1-STORY IRREGULAR SHAPED 27'-2" x 60'-0" 2ND DWELLING UNIT PER SB9 TWO-UNIT DEVELOPEMENT WITH FRONT COVERED PORCH PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
- Permit Issued
- Issued on 3/25/2025
- Issuing Office
- Current Status
- CofO Issued on 11/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2024 | ALFRED RAMIREZ |
| Corrections Issued | 10/19/2024 | ALFRED RAMIREZ |
| Quality Review Completed | 10/24/2024 | STEVEN KIM |
| Building Plans Picked Up | 10/25/2024 | APPLICANT |
| Applicant returned to address corrections | 3/19/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 3/25/2025 | ALFRED RAMIREZ |
| Issued | 3/25/2025 | APPLICANT |
| CofO in Progress | 11/14/2025 | JON MCHUGH |
| Permit Finaled | 11/18/2025 | JOHN JANSON |
| CofO Issued | 11/18/2025 | JOHN JANSON |
| Permit Finaled | 11/18/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/29/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 10/29/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 10/30/2024 | CARLOS RAMIREZ |
| ZI | Cleared | 11/15/2024 | YINGSHI HUANG |
| Senate Bill 9 | Cleared | 11/19/2024 | YINGSHI HUANG |
| Miscellaneous | Cleared | 12/3/2024 | MAX LODER |
| Construction within easement | Cleared | 12/23/2024 | GEVORK KARAPETYAN |
| Hydrant and Access approval | Cleared | 3/3/2025 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lobana,, Singh Maninder Pa; Lic. No.: C50989 | 885 PATRIOT DR #G MOORPARK, CA 93021 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/8/2025 | Partial Inspection | JON MCHUGH |
| Underground Mechanical | 4/22/2025 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 4/30/2025 | Approved | JON MCHUGH |
| Sewer | 4/30/2025 | Approved | JON MCHUGH |
| Special/Order Compliance | 4/30/2025 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Partial Approval | JON MCHUGH |
| Deputy Steel/Welding | 6/13/2025 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 6/24/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 6/24/2025 | Approved | JON MCHUGH |
| Green Building Rough | 6/24/2025 | Approved | JON MCHUGH |
| HVAC-Rough | 6/24/2025 | Approved | JON MCHUGH |
| PLUMBING-Rough | 6/24/2025 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 6/24/2025 | Approved | JON MCHUGH |
| Deputy Drilled-In Anchors | 7/1/2025 | Conditional Approval | JON MCHUGH |
| Insulation | 7/2/2025 | Approved | JON MCHUGH |
| Shower Pan | 7/2/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 7/10/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 7/23/2025 | Approved | JON MCHUGH |
| Underground Mechanical | 7/29/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 10/23/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 10/23/2025 | Corrections Issued | JON MCHUGH |
| Green Building Final | 10/23/2025 | Approved | JON MCHUGH |
| HVAC-Final | 10/23/2025 | Approved | JON MCHUGH |
| PLUMBING-Final | 10/23/2025 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 10/23/2025 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 10/23/2025 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 10/23/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 10/28/2025 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 10/28/2025 | Approved | JON MCHUGH |
| PLUMBING-Final | 10/28/2025 | Approved | JON MCHUGH |
| Service/Power Release | 10/28/2025 | Not Ready for Inspection | JON MCHUGH |
| Final | 11/7/2025 | Partial Approval | MORRIS JACKSON |
| Service/Power Release | 11/7/2025 | Approved | MORRIS JACKSON |
| Final | 11/14/2025 | OK to Issue CofO | JON MCHUGH |