19029 W VINTAGE ST 91324

Certificate Information: 19029 W VINTAGE ST 91324

Application / Permit
24010-20000-04260
Plan Check / Job No.
B24VN19113
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan PROPOSED 45'X25' DETACHED SINGLE FAMILY DWELLING PER SB 9 TWO-UNIT DEVELOPMENT CA GOVT CODE 65852.21. ALL WORK PER WFPP. ***SHALL BE SPRINKLERED PER NFPA 13D***
Permit Issued
Issued on 5/10/2025
Issuing Office
Current Status
CofO Issued on 2/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2024 APPLICANT
Assigned to Plan Check Engineer 10/17/2024 MICHAEL LOPEZ
Corrections Issued 10/30/2024 MICHAEL LOPEZ
Quality Review Completed 10/31/2024 GARO TELMI
Applicant returned to address corrections 4/16/2025 MICHAEL LOPEZ
Plan Check Approved 5/9/2025 MICHAEL LOPEZ
Issued 5/10/2025 APPLICANT
CofO in Progress 2/9/2026 DAVID SCANTLIN
Permit Finaled 2/9/2026 JOHN JANSON
CofO Issued 2/9/2026 JOHN JANSON
Permit Finaled 2/9/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/27/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 1/27/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 1/27/2025 BIAINA HARITUNIAN
Sewer availability Cleared 1/27/2025 BIAINA HARITUNIAN
Senate Bill 9 Cleared 1/28/2025 ASHLEY RODARTE
Hydrant and Access approval Cleared 1/31/2025 PATRICK PEREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/7/2025 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Rough 8/7/2025 Partial Approval KRISTEN CAUSEY
Footing/Foundation/Slab 8/11/2025 Approved KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 8/29/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 8/29/2025 Approved DAVID SCANTLIN
ELECTRICAL-Rough 9/22/2025 Approved DAVID SCANTLIN
HVAC-Rough 9/22/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 10/3/2025 Approved DAVID SCANTLIN
Green Building Rough 10/3/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 10/3/2025 Partial Approval DAVID SCANTLIN
Shower Pan 10/3/2025 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 10/3/2025 Approved DAVID SCANTLIN
Drywall Nailing 11/4/2025 Approved DAVID SCANTLIN
Insulation 11/4/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 11/4/2025 Approved DAVID SCANTLIN
Service/Power Release 11/4/2025 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Final 2/6/2026 Approved DAVID SCANTLIN
Final 2/6/2026 OK to Issue CofO DAVID SCANTLIN
Green Building Final 2/6/2026 Approved DAVID SCANTLIN
HVAC-Final 2/6/2026 Approved DAVID SCANTLIN
PLUMBING-Final 2/6/2026 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 2/6/2026 SGSOV Approved DAVID SCANTLIN
Service/Power Release 2/6/2026 Approved DAVID SCANTLIN