10327 1/2 N WISH AVE 91344

Certificate Information: 10327 1/2 N WISH AVE 91344

Application / Permit
24010-20000-04250
Plan Check / Job No.
B24VN16175
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan 1. (N) 1-STORY ADU. DETACHED ADU PER LAMC 12.22 A.33 (c) and (d). TO BE EQUIPPED WITH NFPA 13D FIRE SRPINKLERS THROUGH OUT.
Permit Issued
Issued on 2/17/2025
Issuing Office
Current Status
CofO Issued on 1/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 ADRIANA LOPEZ
Corrections Issued 10/7/2024 ADRIANA LOPEZ
Quality Review Completed 10/17/2024 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 12/5/2024 ADRIANA LOPEZ
Applicant returned to address corrections 1/22/2025 ADRIANA LOPEZ
Plan Check Approved 1/31/2025 ADRIANA LOPEZ
Plan Check Approved 2/14/2025 ADRIANA LOPEZ
Issued 2/17/2025 APPLICANT
No Progress 1/13/2026 RAUL OLAGI
CofO in Progress 1/13/2026 RAUL OLAGI
No Progress 1/13/2026 RAUL OLAGI
CofO in Progress 1/13/2026 RAUL OLAGI
Permit Finaled 1/20/2026 RUBEN SALAS
CofO Issued 1/20/2026 RUBEN SALAS
Permit Finaled 1/20/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/21/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 10/21/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 12/5/2024 BIAINA HARITUNIAN
Sewer availability Cleared 12/5/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 1/23/2025 WALTER RAMIREZ
Construction within easement Cleared 1/23/2025 WALTER RAMIREZ

Contact Information

Contractor Adu Rc Builders; Lic. No.: 1080967-B       ,
Contractor Ca Construction Group Inc; Lic. No.: 1080967-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/27/2025 Partial Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 3/20/2025 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 3/20/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Approved NICHOLAS TROWBRIDGE
Deputy Wood Construction 4/16/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 5/14/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/14/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 5/14/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 5/14/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 5/14/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 5/14/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/5/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/5/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 6/5/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 6/5/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/5/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 6/5/2025 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 6/5/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/10/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 6/10/2025 Approved NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 6/10/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Rough 6/10/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 6/10/2025 Partial Approval NICHOLAS TROWBRIDGE
PLUMBING-Rough 6/10/2025 Approved NICHOLAS TROWBRIDGE
Insulation 6/13/2025 Approved NICHOLAS TROWBRIDGE
Shower Pan 6/13/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 6/17/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 6/17/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 6/20/2025 Approved LOUIS ESCOTO
Underground Mechanical 8/14/2025 Approved CHRISTOPHER ROJAS
Sewer 9/4/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 9/4/2025 Corrections Issued CHRISTOPHER ROJAS
Underground Mechanical 9/16/2025 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Final 10/31/2025 Corrections Issued CHRISTOPHER ROJAS
Final 10/31/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 10/31/2025 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 10/31/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 10/31/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV No Gas CHRISTOPHER ROJAS
Service/Power Release 10/31/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 10/31/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 1/7/2026 Corrections Issued CHRISTOPHER ROJAS
Final 1/7/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 1/7/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 1/7/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 1/7/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Service/Power Release 1/7/2026 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 1/9/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 1/9/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Final 1/9/2026 Approved CHRISTOPHER ROJAS
Service/Power Release 1/9/2026 Approved CHRISTOPHER ROJAS
Final 1/13/2026 Conditional Approval CHRISTOPHER ROJAS