17417 W MAYFLOWER DR 91344

Certificate Information: 17417 W MAYFLOWER DR 91344

Application / Permit
24010-20000-04216
Plan Check / Job No.
B24VN18826
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2 STORY (40' X 21'-6") SFD PER SB9 TWO-UNIT DEVELOPMENT CA GOVT CODE 65852.21 Fully Sprinklered NFPA-13D
Permit Issued
Issued on 3/10/2025
Issuing Office
Valley
Current Status
Issued on 3/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/4/2024 APPLICANT
Assigned to Plan Check Engineer 10/17/2024 EDWARD MEHRABIAN
Corrections Issued 10/22/2024 EDWARD MEHRABIAN
Quality Review Completed 10/24/2024 OMID HEDAYAT
Building Plans Picked Up 10/29/2024 APPLICANT
Plan Check Approved 2/24/2025 EDWARD MEHRABIAN
Plan Check Approved 3/10/2025 EDWARD MEHRABIAN
Issued 3/10/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/29/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 10/29/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 10/30/2024 CARLOS RAMIREZ
Senate Bill 9 Cleared 10/30/2024 ASHLEY RODARTE
Sewer availability Cleared 10/30/2024 CARLOS RAMIREZ
Hydrant and Access approval Cleared 1/22/2025 KENNETH FRASER
GPI Written Notices Cleared 2/24/2025 EDWARD MEHRABIAN
Grading Pre-Inspection Cleared 2/24/2025 EDWARD MEHRABIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/8/2025 Partial Approval STEVEN BACK
Special/Order Compliance 7/8/2025 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 7/17/2025 Approved STEVEN BACK
Deputy Wood Construction 8/29/2025 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Rough 12/23/2025 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 12/23/2025 Corrections Issued STEVEN BACK
HVAC-Rough 12/23/2025 Corrections Issued STEVEN BACK
PLUMBING-Rough 12/23/2025 Approved STEVEN BACK
Deputy Other (see comments) 1/20/2026 Conditional Approval STEVEN BACK
Deputy Wood Construction 1/20/2026 Conditional Approval STEVEN BACK
BUILDING-Rough-Frame 1/21/2026 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 1/21/2026 Approved STEVEN BACK
Green Building Rough 1/21/2026 Approved STEVEN BACK
HVAC-Rough 1/21/2026 Approved STEVEN BACK
Interior/Exterior Lathing 1/21/2026 Partial Approval STEVEN BACK
Verify Sprinkler Sign Off 1/21/2026 Approved STEVEN BACK
Insulation 1/30/2026 Approved STEVEN BACK
Drywall Nailing 2/20/2026 Approved HENRY KIM
Interior/Exterior Lathing 2/20/2026 Approved HENRY KIM
Shower Pan 2/20/2026 Approved HENRY KIM
Underground Mechanical 3/5/2026 Partial Approval STEVEN BACK
Sewer 3/20/2026 Approved STEVEN BACK
Underground Mechanical 3/20/2026 Approved STEVEN BACK