13787 N GLADSTONE AVE 91342
Certificate Information: 13787 N GLADSTONE AVE 91342
- Application / Permit
- 24010-20000-04208
- Plan Check / Job No.
- B24VN18771
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 61'-6" X 157' IRREGULAR SHAPED 2-STORY SFD W/ 3-CAR GARAGE AND PATIO COVER. NFPA 13R FIRE SPRINKLERS TROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/28/2025
- Issuing Office
- Current Status
- Issued on 8/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2024 | RAPHAEL ROSAS |
| Corrections Issued | 10/24/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 10/24/2024 | STEVEN KIM |
| Building Plans Picked Up | 10/29/2024 | APPLICANT |
| Applicant returned to address corrections | 4/10/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 8/28/2025 | RAPHAEL ROSAS |
| Issued | 8/28/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/20/2024 | EDGAR ALCARAZ |
| Trees in Parkway | Cleared | 2/24/2025 | BRANDON WONG |
| Low Impact Development (LID) | Cleared | 3/5/2025 | ERNEST TSE |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2025 | EDGAR ALCARAZ |
| Permit | Cleared | 3/18/2025 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 3/18/2025 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 3/20/2025 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 3/31/2025 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dermendjian,, Raffi Hrag; Lic. No.: C88261 | 9325 SHOSHONE AVENUE NORTHRIDGE, CA 91325 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/16/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 11/12/2025 | Corrections Issued | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2025 | Partial Approval | KEVIN BERBERYAN |
| PLUMBING-Rough | 12/17/2025 | Partial Approval | KEVIN BERBERYAN |
| PLUMBING-Rough | 12/22/2025 | Partial Inspection | KEVIN BERBERYAN |
| Deputy Wood Construction | 1/22/2026 | Conditional Approval | JOAQUIN GREENOUGH |
| Wood Frame | 1/22/2026 | Partial Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 3/31/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Rough | 3/31/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Wood Frame | 3/31/2026 | Corrections Issued | KEVIN BERBERYAN |