7008 N RUBIO AVE 91406
Certificate Information: 7008 N RUBIO AVE 91406
- Application / Permit
- 24010-20000-04193
- Plan Check / Job No.
- B24VN18687
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 30'-0" X 28'-9" ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) AND APPLICABLE PART 2 OF LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 1/21/2025
- Issuing Office
- Current Status
- CofO Issued on 7/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 10/10/2024 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 1/13/2025 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 1/16/2025 | DANIEL ABRAMYAN |
| Plan Check Approved | 1/20/2025 | DANIEL ABRAMYAN |
| Issued | 1/21/2025 | APPLICANT |
| CofO in Progress | 7/18/2025 | SALVADOR MARTINEZ |
| Permit Finaled | 7/30/2025 | RUBEN SALAS |
| CofO Issued | 7/30/2025 | RUBEN SALAS |
| Permit Finaled | 7/30/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 1/10/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 1/14/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/3/2025 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/21/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Partial Approval | SALVADOR MARTINEZ |
| HVAC-Rough | 4/22/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 4/22/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 4/22/2025 | Approved | SALVADOR MARTINEZ |
| Underground Mechanical | 4/22/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 4/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 5/7/2025 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/7/2025 | Approved | SALVADOR MARTINEZ |
| Underground Mechanical | 5/7/2025 | Approved | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 5/7/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/21/2025 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 5/21/2025 | Approved | SALVADOR MARTINEZ |
| Insulation | 5/21/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 5/21/2025 | Partial Approval | SALVADOR MARTINEZ |
| Drywall Nailing | 5/29/2025 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 5/29/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 6/3/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 7/1/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 7/1/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 7/1/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Final | 7/1/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 7/1/2025 | SGSOV No Gas | SALVADOR MARTINEZ |
| Service/Power Release | 7/1/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 7/1/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 7/11/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 7/11/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 7/11/2025 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 7/11/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Final | 7/17/2025 | OK to Issue CofO | SALVADOR MARTINEZ |
| Service/Power Release | 7/17/2025 | Approved | SALVADOR MARTINEZ |