1369-1371 E 58TH ST 90011
Certificate Information: 1369-1371 E 58TH ST 90011
- Application / Permit
- 24010-20000-04189
- Plan Check / Job No.
- B24VN18627
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX , ATTACHED 1-CAR GARAGE IN THE FRONT AND ATTACHED 2-CAR GARAGE IN THE REAR. TO BE FULLY SPRINKLERED NFPA 13D
- Permit Issued
- Issued on 2/27/2025
- Issuing Office
- Current Status
- CofO Issued on 11/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 10/12/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 10/21/2024 | TU HUA |
| Plan Check Approved | 2/19/2025 | MARCELA FRANQUEZ |
| Issued | 2/27/2025 | APPLICANT |
| CofO in Progress | 10/30/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
| CofO Issued | 11/9/2025 | DEROLD HAUFF |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 10/29/2024 | FIPE LEILUA |
| Address approval | Cleared | 11/19/2024 | JUSTIN BICOL |
| Permit | Cleared | 11/19/2024 | JUSTIN BICOL |
| Low Impact Development (LID) | Cleared | 11/20/2024 | SARAH YOUSSEF |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 12/3/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 12/3/2024 | JUSTIN BICOL |
| Trees in Parkway | Cleared | 12/10/2024 | MIGUEL ORNELAS |
| Hydrant and Access approval | Cleared | 1/29/2025 | FRANK GOMEZ |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/9/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/9/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Insulation | 4/9/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 4/9/2025 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 4/9/2025 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/20/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/20/2025 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 6/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 6/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 6/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/26/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 6/26/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 7/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 7/21/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 7/21/2025 | Approved | RONNIE MEDINA |
| ELECTRICAL-Final | 10/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 10/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/17/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/17/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/20/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 10/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/23/2025 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 10/23/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 10/27/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/27/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/29/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/29/2025 | Approved | ALEJANDRO DE ARTOLA |