1369-1371 E 58TH ST 90011

Certificate Information: 1369-1371 E 58TH ST 90011

Application / Permit
24010-20000-04189
Plan Check / Job No.
B24VN18627
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX , ATTACHED 1-CAR GARAGE IN THE FRONT AND ATTACHED 2-CAR GARAGE IN THE REAR. TO BE FULLY SPRINKLERED NFPA 13D
Permit Issued
Issued on 2/27/2025
Issuing Office
Current Status
CofO Issued on 11/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2024 APPLICANT
Assigned to Plan Check Engineer 10/10/2024 MARCELA FRANQUEZ
Corrections Issued 10/12/2024 MARCELA FRANQUEZ
Quality Review Completed 10/21/2024 TU HUA
Plan Check Approved 2/19/2025 MARCELA FRANQUEZ
Issued 2/27/2025 APPLICANT
CofO in Progress 10/30/2025 ALEJANDRO DE ARTOLA
Permit Finaled 11/9/2025 DEROLD HAUFF
CofO Issued 11/9/2025 DEROLD HAUFF
Permit Finaled 11/9/2025 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 10/29/2024 FIPE LEILUA
Address approval Cleared 11/19/2024 JUSTIN BICOL
Permit Cleared 11/19/2024 JUSTIN BICOL
Low Impact Development (LID) Cleared 11/20/2024 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 12/3/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 12/3/2024 JUSTIN BICOL
Sewer availability Cleared 12/3/2024 JUSTIN BICOL
Trees in Parkway Cleared 12/10/2024 MIGUEL ORNELAS
Hydrant and Access approval Cleared 1/29/2025 FRANK GOMEZ

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/28/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/9/2025 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 4/9/2025 Not Ready for Inspection ALEJANDRO DE ARTOLA
Insulation 4/9/2025 Partial Approval ALEJANDRO DE ARTOLA
Sewer 4/9/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 4/9/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/11/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/20/2025 Approved ENRIQUE MIRELES
PLUMBING-Rough 6/20/2025 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 6/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/23/2025 Approved ALEJANDRO DE ARTOLA
Green Building Rough 6/23/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 6/23/2025 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 6/23/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/26/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/26/2025 Approved ALEJANDRO DE ARTOLA
Insulation 7/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 7/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 7/21/2025 Approved RONNIE MEDINA
Interior/Exterior Lathing 7/21/2025 Approved RONNIE MEDINA
ELECTRICAL-Final 10/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 10/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 10/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 10/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 10/17/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 10/17/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 10/20/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 10/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/23/2025 SGSOV Not Required ALEJANDRO DE ARTOLA
Service/Power Release 10/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 10/23/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/27/2025 Approved ALEJANDRO DE ARTOLA
Final 10/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 10/27/2025 Approved ALEJANDRO DE ARTOLA
Final 10/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 10/28/2025 Approved ALEJANDRO DE ARTOLA
Final 10/29/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
Service/Power Release 10/29/2025 Approved ALEJANDRO DE ARTOLA