6224 N BAKMAN AVE 91606
Certificate Information: 6224 N BAKMAN AVE 91606
- Application / Permit
- 24010-20000-04188
- Plan Check / Job No.
- B24VN18625
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ALL ELECTRIC ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/22/2024
- Issuing Office
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 10/10/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 10/16/2024 | APPLICANT |
| Plan Check Approved | 10/22/2024 | ALEC MOUSAKHANIAN |
| Issued | 10/22/2024 | APPLICANT |
| CofO in Progress | 6/9/2025 | MISAEL ESPARZA |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 10/19/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 10/21/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/10/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 12/23/2024 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2025 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 1/23/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 1/23/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Sewer | 1/23/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 1/23/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 2/18/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 2/18/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 2/19/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 2/26/2025 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 2/26/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 2/27/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 2/27/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 2/27/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 3/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 3/11/2025 | No Access for Inspection | MICHAEL CORTEZ |
| Drywall Nailing | 3/18/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 3/18/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 3/25/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 6/3/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Service/Power Release | 6/3/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 6/6/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 6/6/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 6/6/2025 | SGSOV Not Required | MISAEL ESPARZA |
| Service/Power Release | 6/6/2025 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 6/6/2025 | Approved | MISAEL ESPARZA |