23339 W VICTORY BLVD 91303
Certificate Information: 23339 W VICTORY BLVD 91303
- Application / Permit
- 24010-20000-04143
- Plan Check / Job No.
- B24VN18245
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED, FULLY ELECTRIC ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 3/21/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/19/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2024 | KAMYAR EMAMI |
| Corrections Issued | 10/7/2024 | KAMYAR EMAMI |
| Applicant returned to address corrections | 2/28/2025 | MADISON ODELL |
| Plan Check Approved | 3/12/2025 | MADISON O'DELL |
| Issued | 3/21/2025 | APPLICANT |
| CofO in Progress | 4/22/2026 | GEVORK IPCHYAN |
| No Progress | 5/19/2026 | HENRY KIM |
| CofO in Progress | 5/19/2026 | HENRY KIM |
Permit Application Clearance Information
| Address approval | Cleared | 11/25/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 11/25/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/6/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Avila,, Francisco Javier; Lic. No.: NA5126 | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/28/2025 | Corrections Issued | GEVORK IPCHYAN |
| Underground Mechanical | 5/1/2025 | Partial Approval | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 6/26/2025 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 8/1/2025 | Partial Approval | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2025 | Partial Approval | GEVORK IPCHYAN |
| Verify Sprinkler Sign Off | 8/1/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 8/19/2025 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 9/17/2025 | Approved | GEVORK IPCHYAN |
| Green Building Rough | 9/17/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 9/17/2025 | Partial Approval | GEVORK IPCHYAN |
| Rough-Elec/Plmb/HVAC | 9/17/2025 | Approved | GEVORK IPCHYAN |
| Shower Pan | 9/17/2025 | Approved | GEVORK IPCHYAN |
| Insulation | 9/23/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 10/20/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 10/20/2025 | Partial Approval | GEVORK IPCHYAN |
| Final | 2/12/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 2/12/2026 | SGSOV Not Ready | GEVORK IPCHYAN |
| Service/Power Release | 2/12/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Smoke Detectors | 2/12/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Final | 4/21/2026 | Approved | GEVORK IPCHYAN |
| Final | 4/21/2026 | OK to Issue CofO | GEVORK IPCHYAN |
| HVAC-Final | 4/21/2026 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 4/21/2026 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2026 | SGSOV Approved | GEVORK IPCHYAN |
| Service/Power Release | 4/21/2026 | Approved | GEVORK IPCHYAN |
| Smoke Detectors | 4/21/2026 | Approved | GEVORK IPCHYAN |
| Special/Order Compliance | 5/19/2026 | Corrections Issued | GEVORK IPCHYAN |