20319 W OXNARD ST 91367

Certificate Information: 20319 W OXNARD ST 91367

Application / Permit
24010-20000-04140
Plan Check / Job No.
B24VN18237
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 43'-4" X 24'-4" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d); ADD 110 SQ FT PATIO COVER
Permit Issued
Issued on 7/1/2025
Issuing Office
Current Status
CofO in Progress on 4/27/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/1/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 SELLA BENYAMIN
Corrections Issued 10/8/2024 SELLA BENYAMIN
Quality Review Completed 10/9/2024 STEVEN KIM
Applicant returned to address corrections 12/5/2024 SELLA BENYAMIN
Applicant returned to address corrections 3/18/2025 SELLA BENYAMIN
Plan Check Approved 4/15/2025 SELLA BENYAMIN
Issued 7/1/2025 APPLICANT
CofO in Progress 4/27/2026 ALEXANDER HANDY

Permit Application Clearance Information

Address approval Cleared 10/17/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 10/17/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/23/2024 RYAN CASTRO
Sewer availability Cleared 10/23/2024 RYAN CASTRO

Contact Information

Contractor Bella Adu; Lic. No.: 599288-B       ,
Contractor L&R Home Builders Inc; Lic. No.: 599288-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/26/2025 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 10/29/2025 Partial Approval ALEXANDER HANDY
Footing/Foundation/Slab 11/7/2025 Corrections Issued JUAN ALVARADO
Footing/Foundation/Slab 11/26/2025 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/23/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 1/6/2026 Not Ready for Inspection ALEXANDER HANDY
ELECTRICAL-Rough 1/6/2026 Not Ready for Inspection ALEXANDER HANDY
Green Building Rough 1/6/2026 Not Ready for Inspection ALEXANDER HANDY
HVAC-Rough 1/6/2026 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 1/6/2026 Not Ready for Inspection ALEXANDER HANDY
BUILDING-Rough-Frame 1/8/2026 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 1/8/2026 Approved ALEXANDER HANDY
Green Building Rough 1/8/2026 Approved ALEXANDER HANDY
HVAC-Rough 1/8/2026 Corrections Issued ALEXANDER HANDY
PLUMBING-Rough 1/8/2026 Approved ALEXANDER HANDY
HVAC-Rough 1/21/2026 Conditional Approval ALEXANDER HANDY
BUILDING-Rough-Frame 2/2/2026 Partial Approval ROBERT GOLD
Green Building Rough 2/2/2026 Approved ROBERT GOLD
Interior/Exterior Lathing 2/2/2026 Partial Approval ROBERT GOLD
Insulation 2/5/2026 Corrections Issued ALEXANDER HANDY
Drywall Nailing 2/9/2026 Approved DAVID FASTIGGI
PLUMBING-Rough 3/2/2026 Approved DAVID FASTIGGI
Sewer 3/11/2026 Approved DAVID FASTIGGI
Underground Mechanical 3/11/2026 Approved DAVID FASTIGGI
Underground Mechanical 3/19/2026 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 4/15/2026 Approved ALEXANDER HANDY
ELECTRICAL-Final 4/15/2026 Corrections Issued ALEXANDER HANDY
Final 4/15/2026 Corrections Issued ALEXANDER HANDY
Green Building Final 4/15/2026 Not Ready for Inspection ALEXANDER HANDY
HVAC-Final 4/15/2026 Approved ALEXANDER HANDY
PLUMBING-Final 4/15/2026 Corrections Issued ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 4/15/2026 SGSOV Not Ready ALEXANDER HANDY
Smoke Detectors 4/15/2026 Not Ready for Inspection ALEXANDER HANDY
Special/Order Compliance 4/15/2026 Approved DAVID FASTIGGI
ELECTRICAL-Final 4/23/2026 Approved ALEXANDER HANDY
Final 4/23/2026 OK to Issue CofO ALEXANDER HANDY
Green Building Final 4/23/2026 Approved ALEXANDER HANDY
HVAC-Final 4/23/2026 Approved ALEXANDER HANDY
PLUMBING-Final 4/23/2026 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 4/23/2026 SGSOV No Gas ALEXANDER HANDY
Smoke Detectors 4/23/2026 Approved ALEXANDER HANDY