4825 N FORMAN AVE 91601

Certificate Information: 4825 N FORMAN AVE 91601

Application / Permit
24010-20000-04103
Plan Check / Job No.
B24VN17964
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY IRREGULAR SHAPED 55'-0" x 32'-6" S.F.D. , COVERED PORCH, AND 2-CAR GARAGE PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
Permit Issued
Issued on 1/31/2025
Issuing Office
Valley
Current Status
CofO Issued on 4/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 ALFRED RAMIREZ
Corrections Issued 10/5/2024 ALFRED RAMIREZ
Quality Review Completed 10/10/2024 STEVEN KIM
Building Plans Picked Up 10/10/2024 APPLICANT
Plan Check Approved 1/30/2025 ALFRED RAMIREZ
Issued 1/31/2025 APPLICANT
CofO in Progress 4/7/2026 JOSE AVILA
Permit Finaled 4/28/2026 RUBEN SALAS
CofO Issued 4/28/2026 RUBEN SALAS
Permit Finaled 4/28/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/10/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/10/2024 LEE GUILBEAUX
Sewer availability Cleared 10/10/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/10/2024 LEE GUILBEAUX
Low Impact Development (LID) Cleared 10/30/2024 MARCO SANCHEZ
Hydrant and Access approval Cleared 11/15/2024 GILBERT URREA
Roof/Waste drainage to street Cleared 12/23/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/3/2025 Partial Approval JOSE AVILA
Underground Mechanical 3/3/2025 Partial Approval JOSE AVILA
Pre-Inspection 3/5/2025 Approved ROBERTO PALACIOS-LOPEZ
Deputy Reinf. Concrete 3/17/2025 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 3/18/2025 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 3/27/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/14/2025 Approved JOSE AVILA
Deputy Wood Construction 4/15/2025 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/16/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 4/30/2025 Conditional Approval JOSE AVILA
HVAC-Rough 5/5/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 5/14/2025 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/19/2025 Corrections Issued JOSE AVILA
Underground Mechanical 5/19/2025 Approved JOSE AVILA
Shower Pan 5/28/2025 Not Ready for Inspection MICHAEL CORTEZ
Shower Pan 6/3/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 6/10/2025 Approved JOSE AVILA
Green Building Rough 6/10/2025 Approved JOSE AVILA
Verify Sprinkler Sign Off 6/10/2025 Approved JOSE AVILA
Deck 6/17/2025 Approved JOSE AVILA
Interior/Exterior Lathing 6/26/2025 Approved JOSE AVILA
HVAC-Rough 6/30/2025 Approved LOUIS ESCOTO
Insulation 6/30/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 7/2/2025 Approved MICHAEL CORTEZ
Drywall Nailing 7/8/2025 Approved JOSE AVILA
Pre-Inspection 9/25/2025 Approved JOSE AVILA
HVAC-Final 11/25/2025 Approved JOSE AVILA
ELECTRICAL-Final 12/4/2025 Approved JOSE AVILA
Final 12/11/2025 Corrections Issued JOSE AVILA
Green Building Final 12/11/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV No Gas JOSE AVILA
Service/Power Release 12/11/2025 Approved JOSE AVILA
Smoke Detectors 12/11/2025 Approved JOSE AVILA
Final 1/28/2026 Corrections Issued JOSE AVILA
Final 4/7/2026 OK to Issue CofO JOSE AVILA