6626 N BEVIS AVE 91405

Certificate Information: 6626 N BEVIS AVE 91405

Application / Permit
24010-20000-04085
Plan Check / Job No.
B24VN17878
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (N) IRREGULAR-SHAPED ADDITION AND (E) DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 4/3/2025
Issuing Office
Current Status
CofO Issued on 10/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2024 APPLICANT
Assigned to Plan Check Engineer 10/11/2024 DANIEL ABRAMYAN
Corrections Issued 10/19/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 11/7/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 11/13/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 2/6/2025 ISIS ARGUETA
Plan Check Approved 2/12/2025 PINANK PATEL
Issued 4/3/2025 APPLICANT
CofO in Progress 10/31/2025 RYAN SALAZAR
Permit Finaled 10/31/2025 RUBEN SALAS
CofO Issued 10/31/2025 RUBEN SALAS
Permit Finaled 10/31/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/6/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 11/6/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/12/2024 RYAN CASTRO
Sewer availability Cleared 11/12/2024 RYAN CASTRO
Construction near power lines Cleared 2/4/2025 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/8/2025 Partial Inspection RYAN SALAZAR
PLUMBING-Rough 4/23/2025 Corrections Issued WILLIAM WREN
PLUMBING-Rough 4/25/2025 Partial Approval RYAN SALAZAR
Underground Mechanical 4/29/2025 Approved RYAN SALAZAR
Footing/Foundation/Slab 5/5/2025 Approved RYAN SALAZAR
Underground Mechanical 5/5/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/2/2025 Partial Approval RYAN SALAZAR
Green Building Rough 6/2/2025 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 7/25/2025 Approved MICHEL ABAJAN
Shower Pan 7/25/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 7/29/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 8/5/2025 Approved RYAN SALAZAR
Green Building Rough 8/5/2025 Approved RYAN SALAZAR
HVAC-Rough 8/5/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/5/2025 Partial Approval RYAN SALAZAR
Insulation 8/15/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/15/2025 Approved RYAN SALAZAR
Shower Pan 8/15/2025 Approved RYAN SALAZAR
Drywall Nailing 8/19/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 10/9/2025 Approved RYAN SALAZAR
Final 10/9/2025 Not Ready for Inspection RYAN SALAZAR
Green Building Final 10/9/2025 Approved RYAN SALAZAR
PLUMBING-Final 10/9/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 10/9/2025 Approved RYAN SALAZAR
Final 10/27/2025 OK to Issue CofO RYAN SALAZAR
HVAC-Final 10/27/2025 Approved RYAN SALAZAR
Service/Power Release 10/27/2025 Approved RYAN SALAZAR