5710 N OAKDALE AVE 91367
Certificate Information: 5710 N OAKDALE AVE 91367
- Application / Permit
- 24010-20000-04073
- Plan Check / Job No.
- B24VN17759
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan (N) Detached ADU per GC 66323(a)(2) . To be fully sprinklered NFPA 13D.
- Permit Issued
- Issued on 12/10/2025
- Issuing Office
- Current Status
- Issued on 12/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 10/11/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 10/16/2024 | TU HUA |
| Applicant returned to address corrections | 5/6/2025 | MARCELA FRANQUEZ |
| Plan Check Approved | 12/4/2025 | MARCELA FRANQUEZ |
| Issued | 12/10/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/25/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 12/6/2024 | SARAH YOUSSEF |
| Sewer availability | Cleared | 12/6/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/9/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/10/2025 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Shower Pan | 7/27/2026 |
Inspection Request History
| PLUMBING-Rough | 4/14/2026 | Approved | DAVID SCANTLIN |
| Sewer | 4/14/2026 | Partial Approval | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 4/22/2026 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 4/22/2026 | Not Ready for Inspection | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 4/27/2026 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 4/27/2026 | Approved | JON MCHUGH |
| PLUMBING-Rough | 6/18/2026 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Rough | 7/6/2026 | Approved | JON MCHUGH |
| HVAC-Rough | 7/6/2026 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 7/6/2026 | Partial Approval | JON MCHUGH |
| HVAC-Rough | 7/9/2026 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 7/9/2026 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Rough | 7/17/2026 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 7/20/2026 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Rough | 7/20/2026 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 7/20/2026 | Approved | JON MCHUGH |