6154-6154 1/2 N COLBATH AVE 91401

Certificate Information: 6154-6154 1/2 N COLBATH AVE 91401

Application / Permit
24010-20000-04072
Plan Check / Job No.
B24VN17744
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
[ePlan] NEW 2-STORY ADU PER CA Govt. Code 65852.2(e)(1)(A) AND A SFD UNDER SB 9 UNIT PER TWO UNIT DEVELOPMENT -BLDG SPINKLERED THRU-OUT
Permit Issued
Issued on 4/16/2025
Issuing Office
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 MAHNAZ NOURHASHEMI
Corrections Issued 9/29/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 10/9/2024 TU HUA
Applicant returned to address corrections 1/29/2025 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 2/27/2025 MAHNAZ NOURHASHEMI
Plan Check Approved 4/15/2025 MAHNAZ NOURHASHEMI
Issued 4/16/2025 APPLICANT
CofO in Progress 9/16/2025 RYAN SALAZAR
CofO Issued 11/13/2025 RUBEN SALAS
Permit Finaled 11/13/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/7/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 10/7/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/8/2024 RYAN CASTRO
Sewer availability Cleared 10/8/2024 RYAN CASTRO
Hydrant and Access approval Cleared 1/2/2025 JERRY KAO
Construction near power lines Cleared 4/4/2025 GEVORK KARAPETYAN
Construction within easement Cleared 4/4/2025 GEVORK KARAPETYAN
Senate Bill 9 Cleared 4/15/2025 JASON CHAN

Contact Information

Contractor Silva Design Construction Inc; Lic. No.: 956083-B       ,
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 8232 GARVEY AVE 203      ROSEMEAD, CA 91770

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/17/2025 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 4/22/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Partial Approval RYAN SALAZAR
Deputy Wood Construction 5/1/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 5/12/2025 Corrections Issued RYAN SALAZAR
ELECTRICAL-Rough 5/12/2025 Approved RYAN SALAZAR
HVAC-Rough 5/12/2025 Approved RYAN SALAZAR
PLUMBING-Rough 5/12/2025 Conditional Approval RYAN SALAZAR
Insulation 5/19/2025 Partial Approval JACK KARGODORIAN
Insulation 5/20/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/20/2025 Approved RYAN SALAZAR
Shower Pan 5/20/2025 Approved RYAN SALAZAR
Drywall Nailing 5/22/2025 Approved RYAN SALAZAR
Sewer 6/27/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 9/3/2025 Approved RYAN SALAZAR
Final 9/3/2025 Corrections Issued RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 9/3/2025 SGSOV Not Required RYAN SALAZAR
Service/Power Release 9/3/2025 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 9/3/2025 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 9/3/2025 Approved RYAN SALAZAR
Final 9/15/2025 OK to Issue CofO RYAN SALAZAR
Service/Power Release 9/15/2025 Approved RYAN SALAZAR