11145 W COHASSET ST 91352

Certificate Information: 11145 W COHASSET ST 91352

Application / Permit
24010-20000-04067
Plan Check / Job No.
B24VN17708
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW 35'1" X 30' ONE STORY DETACHED ACCESSORY LIVING QUARTERS , NFPA-13R FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING- SEE COMMENTS
Permit Issued
Issued on 2/21/2025
Issuing Office
Valley
Current Status
CofO Issued on 3/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2024 APPLICANT
Assigned to Plan Check Engineer 10/10/2024 RARES BODEA
Corrections Issued 10/18/2024 RARES BODEA
Quality Review Completed 10/30/2024 STEVEN KIM
Building Plans Picked Up 10/31/2024 APPLICANT
Applicant returned to address corrections 12/17/2024 RARES BODEA
Applicant returned to address corrections 1/14/2025 RARES BODEA
Plan Check Approved 2/21/2025 RARES BODEA
Issued 2/21/2025 APPLICANT
CofO in Progress 2/25/2026 ROBERTO PALACIOS-LOPEZ
Permit Finaled 3/5/2026 RUBEN SALAS
CofO Issued 3/5/2026 RUBEN SALAS
Permit Finaled 3/5/2026 RUBEN SALAS

Permit Application Clearance Information

Tract Map conditions Cleared 10/18/2024 NATHAN ROMINE
ZI Cleared 10/18/2024 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 10/19/2024 CARLOS AGUILERA
Sewer availability Cleared 10/19/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 10/30/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 10/30/2024 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/29/2025 JERRY KAO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/25/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/25/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Pre-Inspection 2/25/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 2/25/2025 Approved ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 2/28/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 3/3/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/9/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 4/30/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 4/30/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 4/30/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/30/2025 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 4/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 4/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 4/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 5/28/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 5/28/2025 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 5/28/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 6/3/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 6/3/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 12/23/2025 Corrections Issued JOAQUIN GREENOUGH
HVAC-Final 12/23/2025 Approved JOSE AVILA
ELECTRICAL-Final 1/28/2026 Conditional Approval JOSE AVILA
BUILDING-Rough-Frame 2/4/2026 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 2/4/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 2/4/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 2/4/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 2/4/2026 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 2/4/2026 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 2/4/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 2/4/2026 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 2/4/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 2/24/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Green Building Final 2/24/2026 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 2/24/2026 Approved ROBERTO PALACIOS-LOPEZ