704-704 1/2 E 50TH ST 90011
Certificate Information: 704-704 1/2 E 50TH ST 90011
- Application / Permit
- 24010-20000-04063
- Plan Check / Job No.
- B24VN17665
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY 2-ACCESSORY DWELLING UNITS PER GCS65852.2(e)(1)(D) & LAMC 12.22 A.33(c)(d)(g) (ALL WORK PER WFPP) **ePlan**
- Permit Issued
- Issued on 11/6/2024
- Issuing Office
- Current Status
- CofO Issued on 5/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/5/2024 | NILOOFAR MEHRAIN |
| Quality Review Completed | 10/10/2024 | JASON HEALEY |
| Plan Check Approved | 10/23/2024 | NILOOFAR MEHRAIN |
| Issued | 11/6/2024 | APPLICANT |
| CofO in Progress | 4/30/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
| CofO Issued | 5/3/2025 | DEROLD HAUFF |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/15/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 10/15/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 10/15/2024 | JUSTIN BICOL |
Contact Information
| Contractor | So Cal Construction Enterprises Inc; Lic. No.: 832488-B | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 11/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 11/22/2024 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Verify Rec and Parks Fee Memo | 12/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 12/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 12/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 12/20/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/20/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 12/24/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 12/31/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/15/2025 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 1/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/28/2025 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 2/28/2025 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 3/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/5/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/29/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 4/29/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/29/2025 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/29/2025 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 4/29/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/30/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |