6208 N TUJUNGA AVE 91606
Certificate Information: 6208 N TUJUNGA AVE 91606
- Application / Permit
- 24010-20000-04037
- Plan Check / Job No.
- B24VN17485
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 39'-2" X 26'-3" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 1/14/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 9/30/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 10/2/2024 | APPLICANT |
| Applicant returned to address corrections | 11/7/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 1/14/2025 | ALEC MOUSAKHANIAN |
| Issued | 1/14/2025 | APPLICANT |
| CofO in Progress | 8/8/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 8/28/2025 | RUBEN SALAS |
| CofO Issued | 8/28/2025 | RUBEN SALAS |
| Permit Finaled | 8/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2024 | BIAINA HARITUNIAN |
| Miscellaneous | Cleared | 10/19/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 10/19/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 10/22/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 12/18/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/27/2025 | Partial Inspection | MISAEL ESPARZA |
| Pre-Inspection | 1/27/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 1/30/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 1/30/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 2/3/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 2/3/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 2/3/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 2/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 2/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 4/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 4/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 4/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 4/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 4/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 4/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 4/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 4/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 5/1/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 5/1/2025 | Partial Approval | MICHAEL CORTEZ |
| Drywall Nailing | 5/6/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 5/6/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 5/6/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 5/23/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Sewer | 6/9/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 6/9/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 7/22/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 7/22/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 7/22/2025 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 7/22/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 7/22/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 8/4/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 8/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 8/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 8/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |