6208 N TUJUNGA AVE 91606

Certificate Information: 6208 N TUJUNGA AVE 91606

Application / Permit
24010-20000-04037
Plan Check / Job No.
B24VN17485
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 39'-2" X 26'-3" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 1/14/2025
Issuing Office
Valley
Current Status
CofO Issued on 8/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2024 APPLICANT
Assigned to Plan Check Engineer 9/30/2024 ARTIN ZARUKIAN
Corrections Issued 9/30/2024 ARTIN ZARUKIAN
Building Plans Picked Up 10/2/2024 APPLICANT
Applicant returned to address corrections 11/7/2024 ALEC MOUSAKHANIAN
Plan Check Approved 1/14/2025 ALEC MOUSAKHANIAN
Issued 1/14/2025 APPLICANT
CofO in Progress 8/8/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 8/28/2025 RUBEN SALAS
CofO Issued 8/28/2025 RUBEN SALAS
Permit Finaled 8/28/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/19/2024 BIAINA HARITUNIAN
Miscellaneous Cleared 10/19/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 10/19/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/22/2024 BIAINA HARITUNIAN
Sewer availability Cleared 10/22/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 12/18/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/27/2025 Partial Inspection MISAEL ESPARZA
Pre-Inspection 1/27/2025 Approved MISAEL ESPARZA
PLUMBING-Rough 1/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 1/30/2025 Approved ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 2/3/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 2/3/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/3/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 2/11/2025 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 2/11/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/24/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 4/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/7/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/15/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 4/15/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 4/15/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 4/15/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/15/2025 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 4/15/2025 Approved ROBERTO PALACIOS-LOPEZ
Wood Frame 4/15/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 5/1/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 5/1/2025 Partial Approval MICHAEL CORTEZ
Drywall Nailing 5/6/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 5/6/2025 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 5/6/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Shower Pan 5/23/2025 Approved ROBERTO PALACIOS-LOPEZ
Sewer 6/9/2025 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 6/9/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 7/22/2025 Corrections Issued JACK KARGODORIAN
Green Building Final 7/22/2025 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 7/22/2025 SGSOV Approved JACK KARGODORIAN
Service/Power Release 7/22/2025 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 7/22/2025 Not Ready for Inspection JACK KARGODORIAN
Final 8/4/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Green Building Final 8/4/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 8/4/2025 Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 8/4/2025 Approved ROBERTO PALACIOS-LOPEZ