10719 W SYLVAN ST 91606

Certificate Information: 10719 W SYLVAN ST 91606

Application / Permit
24010-20000-03980
Plan Check / Job No.
B24VN17143
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY DETACHED 23'-8" x 23'-3" ACCESSORY DWELLING UNIT TO COMPLY CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 11/12/2024
Issuing Office
Current Status
CofO Issued on 6/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 ALFRED RAMIREZ
Corrections Issued 10/8/2024 ALFRED RAMIREZ
Quality Review Completed 10/15/2024 STEVEN KIM
Building Plans Picked Up 10/16/2024 APPLICANT
Applicant returned to address corrections 11/5/2024 ALFRED RAMIREZ
Plan Check Approved 11/12/2024 ALFRED RAMIREZ
Issued 11/12/2024 APPLICANT
CofO in Progress 5/30/2025 ROBERTO PALACIOS-LOPEZ
CofO Issued 6/18/2025 RUBEN SALAS
Permit Finaled 6/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/28/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/28/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/28/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/30/2024 LEE GUILBEAUX
Sewer availability Cleared 10/30/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/12/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 12/12/2024 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 12/19/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 12/27/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 1/17/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 1/27/2025 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 1/27/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 1/27/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 1/31/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 1/31/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 1/31/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 2/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 2/10/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/10/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
Underground Mechanical 2/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 2/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 3/6/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/12/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Drywall Nailing 3/12/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/12/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 3/12/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/12/2025 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 3/12/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/14/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 5/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 5/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 5/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 5/14/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 5/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 5/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 5/20/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 5/22/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 5/22/2025 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 5/22/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 5/30/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ