12315 W MILBANK ST 91604

Certificate Information: 12315 W MILBANK ST 91604

Application / Permit
24010-20000-03973
Plan Check / Job No.
B24VN17082
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 46'-6" X 86'-7" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ATTACHED TRELLIS; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/25/2025
Issuing Office
Current Status
CofO Issued on 6/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 SELLA BENYAMIN
Corrections Issued 10/1/2024 SELLA BENYAMIN
Quality Review Completed 10/3/2024 STEVEN KIM
Building Plans Picked Up 10/7/2024 APPLICANT
Applicant returned to address corrections 3/4/2025 SELLA BENYAMIN
Plan Check Approved 3/25/2025 SELLA BENYAMIN
Issued 3/25/2025 APPLICANT
CofO in Progress 5/14/2026 CHRISTOPHE COCHRAN
CofO Issued 6/10/2026 RUBEN SALAS
Permit Finaled 6/10/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/10/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/11/2024 RYAN CASTRO
Sewer availability Cleared 10/11/2024 RYAN CASTRO
Permit Cleared 11/15/2024 RYAN CASTRO
Trees in Parkway Cleared 11/15/2024 MIGUEL ORNELAS
ZI Cleared 11/22/2024 ASHLEY RODARTE
Hydrant and Access approval Cleared 1/9/2025 JERRY KAO

Contact Information

Architect Sennikoff,, Steven B; Lic. No.: C27650 5500 EAST 2ND ST. SUITE 2      LONG BEACH, CA 90803
Contractor Dwell Llc; Lic. No.: 1030158-B 5315 LAUREL CANYON BLVD #102      VALLEY VILLAGE, CA 91607
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/3/2025 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/6/2025 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 6/16/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 6/16/2025 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 6/17/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/27/2025 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 7/28/2025 Partial Approval JACK KARGODORIAN
Green Building Rough 7/28/2025 Approved JACK KARGODORIAN
MERV13>=Rough 7/28/2025 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 7/28/2025 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 8/12/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 8/18/2025 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 8/18/2025 Approved CHRISTOPHE COCHRAN
Deputy Wood Construction 8/21/2025 Conditional Approval JUAN VALENZUELA
Shower Pan 8/29/2025 Approved JACK KARGODORIAN
ELECTRICAL-Rough 9/4/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 9/9/2025 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/11/2025 Partial Approval CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 9/11/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 9/16/2025 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/8/2025 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 10/8/2025 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/21/2025 Approved JACK KARGODORIAN
Insulation 10/21/2025 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 10/21/2025 Approved JACK KARGODORIAN
Drywall Nailing 10/27/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/1/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Final 5/1/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Final 5/1/2026 Approved CHRISTOPHE COCHRAN
Final 5/8/2026 Partial Inspection CHRISTOPHE COCHRAN
Green Building Final 5/8/2026 Approved CHRISTOPHE COCHRAN
MERV13>=Final 5/8/2026 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 5/8/2026 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 5/8/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 5/8/2026 Approved CHRISTOPHE COCHRAN
Final 5/13/2026 OK to Issue CofO CHRISTOPHE COCHRAN
Service/Power Release 5/13/2026 Approved CHRISTOPHE COCHRAN