19529 W STRATHERN ST 91335

Certificate Information: 19529 W STRATHERN ST 91335

Application / Permit
24010-20000-03963
Plan Check / Job No.
B24VN17042
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New irregular shaped one story 41' 7" x 35' 9" ADU per GC 66323(a)(4). NFPA 13D sprinkler required. All work done per engineer.
Permit Issued
Issued on 2/12/2025
Issuing Office
Current Status
CofO Issued on 2/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 NAREG ATARIAN
Corrections Issued 9/29/2024 NAREG ATARIAN
Quality Review Completed 10/8/2024 RARES BODEA
Building Plans Picked Up 10/9/2024 APPLICANT
Applicant returned to address corrections 11/20/2024 NAREG ATARIAN
Plan Check Approved 2/12/2025 NAREG ATARIAN
Issued 2/12/2025 APPLICANT
CofO in Progress 1/27/2026 ARUTYUN MADATYAN
Permit Finaled 2/26/2026 JOHN JANSON
CofO Issued 2/26/2026 JOHN JANSON
Permit Finaled 2/26/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/22/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 10/22/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/24/2024 RYAN CASTRO
Sewer availability Cleared 10/24/2024 RYAN CASTRO
Hydrant and Access approval Cleared 2/12/2025 FRANK GOMEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/25/2025 Approved ARUTYUN MADATYAN
Footing/Foundation/Slab 4/25/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 4/25/2025 Partial Approval ARUTYUN MADATYAN
Deputy Wood Construction 5/19/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 5/19/2025 Corrections Issued ARUTYUN MADATYAN
ELECTRICAL-Rough 6/6/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 6/6/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 6/16/2025 Approved ARUTYUN MADATYAN
HVAC-Rough 6/16/2025 Approved ARUTYUN MADATYAN
Shower Pan 6/16/2025 Not Ready for Inspection ARUTYUN MADATYAN
Interior/Exterior Lathing 6/26/2025 Not Ready for Inspection JUAN ALVARADO
Shower Pan 6/26/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 7/2/2025 Partial Approval ROBERT GOLD
Green Building Rough 7/2/2025 Approved ROBERT GOLD
Interior/Exterior Lathing 7/2/2025 Partial Approval ROBERT GOLD
Verify Sprinkler Sign Off 7/2/2025 Approved ROBERT GOLD
BUILDING-Rough-Frame 7/15/2025 No Access for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 7/18/2025 Approved ARUTYUN MADATYAN
Insulation 7/18/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 7/23/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 7/23/2025 Approved ARUTYUN MADATYAN
Gas Test 8/14/2025 Not Ready for Inspection ARUTYUN MADATYAN
Underground Mechanical 8/14/2025 Approved ARUTYUN MADATYAN
Underground Mechanical 9/19/2025 No Access for Inspection KRISTEN CAUSEY
ELECTRICAL-Final 12/4/2025 Not Ready for Inspection ARUTYUN MADATYAN
Final 12/4/2025 Corrections Issued ARUTYUN MADATYAN
HVAC-Final 12/4/2025 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Final 1/20/2026 Approved ARUTYUN MADATYAN
Final 1/20/2026 Not Ready for Inspection ARUTYUN MADATYAN
Gas Test 1/20/2026 No Access for Inspection ARUTYUN MADATYAN
Green Building Final 1/20/2026 Approved ARUTYUN MADATYAN
HVAC-Final 1/20/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 1/20/2026 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 1/20/2026 SGSOV No Gas ARUTYUN MADATYAN
Service/Power Release 1/20/2026 Approved ARUTYUN MADATYAN
Smoke Detectors 1/20/2026 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 1/26/2026 Approved ARUTYUN MADATYAN
Final 1/26/2026 OK to Issue CofO ARUTYUN MADATYAN
Gas Test 1/26/2026 Approved ARUTYUN MADATYAN
HVAC-Final 1/26/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 1/26/2026 Approved ARUTYUN MADATYAN