23032 W COLLINS ST 91367

Certificate Information: 23032 W COLLINS ST 91367

Application / Permit
24010-20000-03920
Plan Check / Job No.
B24VN16678
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 48'-0" X 18'-0" DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) *NFPA-13D FIRE SPRINKLERED THROUGHOUT
Permit Issued
Issued on 11/15/2024
Issuing Office
Current Status
CofO Issued on 9/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2024 APPLICANT
Assigned to Plan Check Engineer 9/23/2024 JEROME MAGAT PALMA
Corrections Issued 9/25/2024 JEROME MAGAT PALMA
Building Plans Picked Up 9/27/2024 APPLICANT
Applicant returned to address corrections 10/24/2024 ALEC MOUSAKHANIAN
Issued 11/15/2024 APPLICANT
CofO in Progress 5/5/2025 TROY SANDERS
Permit Finaled 9/6/2025 MICHAEL PELHAM
CofO Issued 9/6/2025 MICHAEL PELHAM
Permit Finaled 9/6/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 10/1/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 10/1/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/2/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 10/2/2024 CHARLES POWELL
Miscellaneous Cleared 10/15/2024 BRENNEN OBETO
Private sewage disp. approval Cleared 10/22/2024 MICHAEL TEMPLE
GPI Written Notices Cleared 11/12/2024 JEROME MAGAT PALMA

Contact Information

Contractor Ci La Construction Inc; Lic. No.: 1097004-B 5354 VANALDEN AVENUE      TARZANA, CA 91356
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/26/2024 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 11/26/2024 Partial Approval TROY SANDERS
Footing/Foundation/Slab 12/2/2024 Approved TROY SANDERS
BUILDING-Rough-Frame 12/19/2024 Not Ready for Inspection TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/19/2024 Partial Approval TROY SANDERS
Green Building Rough 12/19/2024 Not Ready for Inspection TROY SANDERS
Verify Sprinkler Sign Off 12/19/2024 Not Ready for Inspection TROY SANDERS
ELECTRICAL-Rough 12/24/2024 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/24/2024 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 1/23/2025 Approved TROY SANDERS
Green Building Rough 1/23/2025 Approved TROY SANDERS
HVAC-Rough 1/23/2025 Approved TROY SANDERS
Interior/Exterior Lathing 1/23/2025 Partial Approval TROY SANDERS
PLUMBING-Rough 1/23/2025 Approved TROY SANDERS
Verify Sprinkler Sign Off 1/23/2025 Approved TROY SANDERS
Drywall Nailing 2/11/2025 Approved TROY SANDERS
Shower Pan 2/28/2025 Approved TROY SANDERS
Interior/Exterior Lathing 3/3/2025 Partial Approval TROY SANDERS
ELECTRICAL-Final 4/25/2025 Approved TROY SANDERS
HVAC-Final 4/25/2025 Approved TROY SANDERS
Final 5/2/2025 OK to Issue CofO TROY SANDERS
Green Building Final 5/2/2025 Approved TROY SANDERS
PLUMBING-Final 5/2/2025 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Approved TROY SANDERS
Service/Power Release 5/2/2025 Approved TROY SANDERS
Smoke Detectors 5/2/2025 Approved TROY SANDERS