4623 N ATOLL AVE 91423
Certificate Information: 4623 N ATOLL AVE 91423
- Application / Permit
- 24010-20000-03889
- Plan Check / Job No.
- B24VN16489
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New two story irregular shaped 72' 10 11/16" x 34' Single Family dwelling, with attached garage, and trellis. NFPA 13D sprinkler required throughout.
- Permit Issued
- Issued on 2/27/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | NAREG ATARIAN |
| Corrections Issued | 9/22/2024 | NAREG ATARIAN |
| Quality Review Completed | 9/30/2024 | DAWN MC NULTY |
| Building Plans Picked Up | 10/4/2024 | APPLICANT |
| Applicant returned to address corrections | 12/27/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 2/18/2025 | NAREG ATARIAN |
| Plan Check Approved | 2/24/2025 | NAREG ATARIAN |
| Issued | 2/27/2025 | APPLICANT |
| No Progress | 2/21/2026 | RAUL OLAGI |
| CofO in Progress | 2/21/2026 | RAUL OLAGI |
| Permit Finaled | 3/10/2026 | RUBEN SALAS |
| CofO Issued | 3/10/2026 | RUBEN SALAS |
| Permit Finaled | 3/10/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/26/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 11/26/2024 | RYAN CASTRO |
| ZI | Cleared | 12/2/2024 | ALEX VELA |
| Address approval | Cleared | 12/3/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 12/3/2024 | RYAN CASTRO |
| Trees in Parkway | Cleared | 1/29/2025 | MIGUEL ORNELAS |
| Hydrant and Access approval | Cleared | 2/6/2025 | FRANK GOMEZ |
| Permit | Cleared | 2/22/2025 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 4/3/2025 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 4/3/2025 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 4/18/2025 | Approved | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 4/22/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 6/20/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 7/1/2025 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 7/17/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 7/22/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 7/22/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 7/30/2025 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 7/30/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 7/31/2025 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/1/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 8/1/2025 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 8/1/2025 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 8/1/2025 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 8/6/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/12/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 8/15/2025 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 8/21/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Drywall Nailing | 8/26/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/26/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 12/19/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Not Ready | JAVIER RAMOS JR |
| Final | 1/12/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 1/12/2026 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Final | 1/12/2026 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 1/12/2026 | SGSOV Not Required | CHRISTOPHE COCHRAN |
| Service/Power Release | 1/12/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 1/12/2026 | Approved | CHRISTOPHE COCHRAN |
| Final | 1/16/2026 | Conditional Approval | CHRISTOPHE COCHRAN |
| Service/Power Release | 1/16/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Service/Power Release | 2/9/2026 | Approved | CHRISTOPHE COCHRAN |