14215 W HUBBARD ST 91342

Certificate Information: 14215 W HUBBARD ST 91342

Application / Permit
24010-20000-03881
Plan Check / Job No.
B24VN16443
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
[ePlan] NEW 2-STORY ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 3/5/2025
Issuing Office
Current Status
Issued on 3/5/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/16/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 MAHNAZ NOURHASHEMI
Corrections Issued 9/29/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 10/8/2024 TU HUA
Applicant returned to address corrections 11/3/2024 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 1/13/2025 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 2/24/2025 MAHNAZ NOURHASHEMI
Plan Check Approved 2/24/2025 MAHNAZ NOURHASHEMI
Issued 3/5/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/13/2024 TAL SHEMEN
Roof/Waste drainage to street Cleared 10/13/2024 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 10/15/2024 TAL SHEMEN
Sewer availability Cleared 10/15/2024 TAL SHEMEN

Contact Information

Contractor Cali Remodeling; Lic. No.: 1061730-B       ,
Contractor G E J Construction Inc; Lic. No.: 1061730-B       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/14/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 4/14/2025 Partial Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 4/18/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 6/27/2025 Corrections Issued JENNIFER RABUCHIN
Shower Pan 6/27/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 8/5/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 8/5/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/5/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/11/2025 Partial Approval JENNIFER RABUCHIN
Green Building Rough 8/11/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 8/11/2025 Approved JENNIFER RABUCHIN
Insulation 8/11/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 8/11/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 8/11/2025 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 8/11/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 8/28/2025 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/19/2026 Approved JENNIFER RABUCHIN
Final 5/19/2026 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 5/19/2026 Approved JENNIFER RABUCHIN
Green Building Final 5/19/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/19/2026 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 5/19/2026 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 5/19/2026 Approved JENNIFER RABUCHIN
Gas Test 6/25/2026 Approved JENNIFER RABUCHIN
Final 7/9/2026 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 7/9/2026 SGSOV Not Ready RAUL OLAGI
Service/Power Release 7/9/2026 Not Ready for Inspection RAUL OLAGI