22347 W MANDELL ST 91304

Certificate Information: 22347 W MANDELL ST 91304

Application / Permit
24010-20000-03865
Plan Check / Job No.
B24VN16334
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRR. SHAPED 27' x 43' DET. ONE-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 12/14/2024
Issuing Office
Current Status
CofO Issued on 3/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 SEAN SHAHMIRI
Corrections Issued 10/2/2024 SEAN SHAHMIRI
Quality Review Completed 10/3/2024 STEVEN KIM
Plan Check Approved 12/13/2024 SEAN SHAHMIRI
Issued 12/14/2024 APPLICANT
CofO in Progress 3/6/2026 JEFFREY HARTLINE
Permit Finaled 3/12/2026 JOHN JANSON
CofO Issued 3/12/2026 JOHN JANSON
Permit Finaled 3/12/2026 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/25/2024 RYAN CASTRO
Address approval Cleared 11/26/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/26/2024 RYAN CASTRO
Sewer availability Cleared 11/26/2024 RYAN CASTRO
Construction within easement Cleared 12/10/2024 RIDWAN HARDY
Grading Pre-Inspection Cleared 12/13/2024 SEAN SHAHMIRI

Contact Information

Contractor Owner-Builder       ,
Engineer Ebrahimian, Dehaghani, Mahdi; Lic. No.: C86987 19300 RINALDI ST, P.O. BOX 8401      PORTER RANCH, CA 91327

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/14/2025 Partial Approval JEFFREY HARTLINE
Underground Mechanical 1/17/2025 Partial Approval JEFFREY HARTLINE
Footing/Foundation/Slab 1/31/2025 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Rough 3/12/2025 Approved JEFFREY HARTLINE
HVAC-Rough 3/12/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 3/17/2025 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Approved JEFFREY HARTLINE
Rough-Elec/Plmb/HVAC 5/2/2025 Approved JEFFREY HARTLINE
Underground Mechanical 5/2/2025 Partial Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 5/9/2025 Approved JEFFREY HARTLINE
Green Building Rough 5/9/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 5/9/2025 Partial Approval JEFFREY HARTLINE
Verify Sprinkler Sign Off 5/9/2025 Approved JEFFREY HARTLINE
Insulation 5/14/2025 Approved JEFFREY HARTLINE
Drywall Nailing 5/21/2025 Approved CHRIS CHRISTENSEN
Shower Pan 5/21/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/4/2025 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/9/2025 Corrections Issued JEFFREY HARTLINE
ELECTRICAL-Rough 8/13/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 2/23/2026 Not Ready for Inspection JEFFREY HARTLINE
Final 3/5/2026 OK to Issue CofO JEFFREY HARTLINE
Green Building Final 3/5/2026 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 3/5/2026 SGSOV Approved JEFFREY HARTLINE
Service/Power Release 3/5/2026 Approved JEFFREY HARTLINE
Smoke Detectors 3/5/2026 Approved JEFFREY HARTLINE