7702 N ARCOLA AVE 91352

Certificate Information: 7702 N ARCOLA AVE 91352

Application / Permit
24010-20000-03852
Plan Check / Job No.
B24VN16239
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN NEW 31' X 41' 1-STORY SFD per SB9 Two-Unit Development Ca Govt Code 65852.21. NFPA 13R FIRE SPRINKLERS THROUGHOUT. ALL WORK PER WFPP.
Permit Issued
Issued on 11/21/2025
Issuing Office
Current Status
Issued on 11/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/11/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 RAPHAEL ROSAS
Corrections Issued 10/4/2024 RAPHAEL ROSAS
Quality Review Completed 10/9/2024 STEVEN KIM
Applicant returned to address corrections 11/4/2025 RAPHAEL ROSAS
Plan Check Approved 11/12/2025 RAPHAEL ROSAS
Issued 11/21/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 1/27/2025 ENRIQUE ACOSTA
Hydrant and Access approval Cleared 10/1/2025 JERRY KAO
Senate Bill 9 Cleared 10/2/2025 YINGSHI HUANG
Address approval Cleared 10/14/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/14/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/14/2025 LEE GUILBEAUX
Sewer availability Cleared 10/14/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/14/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/2/2025 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 2/26/2026 Partial Approval DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 3/5/2026 Approved DAVID ANDERSON
BUILDING-Rough-Frame 5/4/2026 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 5/4/2026 Approved DAVID ANDERSON
Green Building Rough 5/4/2026 Approved DAVID ANDERSON
HVAC-Rough 5/4/2026 Approved DAVID ANDERSON
PLUMBING-Rough 5/4/2026 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 5/4/2026 Corrections Issued DAVID ANDERSON
Sewer 5/13/2026 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 5/28/2026 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 5/28/2026 Approved DAVID ANDERSON
Sewer 5/28/2026 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 5/28/2026 Approved DAVID ANDERSON
Insulation 6/5/2026 Approved DAVID ANDERSON
Interior/Exterior Lathing 6/5/2026 Partial Approval DAVID ANDERSON