10327 1/4 N WISH AVE 91344
Certificate Information: 10327 1/4 N WISH AVE 91344
- Application / Permit
- 24010-20000-03844
- Plan Check / Job No.
- B24VN16175
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan 1. (N) 1-STORY SB9 UNIT PER SB9 TWO-UNIT DEVELOPMENT. TO BE EQUIPPED WITH NFPA 13D FIRE SRPINKLERS THROUGH OUT.
- Permit Issued
- Issued on 2/5/2025
- Issuing Office
- Current Status
- CofO Issued on 1/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2024 | ADRIANA LOPEZ |
| Corrections Issued | 10/7/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 10/17/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 12/5/2024 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 1/22/2025 | ADRIANA LOPEZ |
| Plan Check Approved | 1/31/2025 | ADRIANA LOPEZ |
| Issued | 2/5/2025 | APPLICANT |
| CofO in Progress | 1/13/2026 | CHRISTOPHER ROJAS |
| Permit Finaled | 1/20/2026 | RUBEN SALAS |
| CofO Issued | 1/20/2026 | RUBEN SALAS |
| Permit Finaled | 1/20/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 10/21/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/5/2024 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 12/19/2024 | KURT CORRAL |
| Senate Bill 9 | Cleared | 12/30/2024 | DORIAN AGUILAR |
| Construction near power lines | Cleared | 1/23/2025 | WALTER RAMIREZ |
| Construction within easement | Cleared | 1/23/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Adu Rc Builders; Lic. No.: 1080967-B | , |
| Contractor | Ca Construction Group Inc; Lic. No.: 1080967-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: NA93079 | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/27/2025 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 3/20/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/20/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 3/24/2025 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Approved | NICHOLAS TROWBRIDGE |
| Deputy Wood Construction | 4/16/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/14/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/14/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 5/14/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 5/14/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/14/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 5/14/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/5/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 6/5/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 6/5/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 6/5/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 6/5/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 6/5/2025 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 6/5/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/10/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 6/10/2025 | Conditional Approval | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 6/10/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 6/10/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 6/10/2025 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 6/13/2025 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 6/13/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 6/17/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 6/17/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 6/20/2025 | Approved | LOUIS ESCOTO |
| Underground Mechanical | 8/14/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Sewer | 9/4/2025 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 9/16/2025 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/31/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 10/31/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 10/31/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 10/31/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 10/31/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 10/31/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 10/31/2025 | SGSOV No Gas | CHRISTOPHER ROJAS |
| Service/Power Release | 10/31/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 10/31/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 1/7/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 1/7/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 1/7/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 1/7/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 1/7/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Service/Power Release | 1/7/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 1/9/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 1/9/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 1/9/2026 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 1/9/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 1/13/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |