10260 N LUBAO AVE 91311

Certificate Information: 10260 N LUBAO AVE 91311

Application / Permit
24010-20000-03836
Plan Check / Job No.
B24VN16121
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 10/15/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2024 APPLICANT
Assigned to Plan Check Engineer 9/13/2024 JEROME MAGAT PALMA
Corrections Issued 9/14/2024 JEROME MAGAT PALMA
Building Plans Picked Up 9/18/2024 APPLICANT
Plan Check Approved 9/24/2024 PINANK PATEL
Issued 10/15/2024 APPLICANT
CofO in Progress 12/17/2025 DAVID SCANTLIN
Permit Finaled 12/20/2025 MICHAEL PELHAM
CofO Issued 12/20/2025 MICHAEL PELHAM
Permit Finaled 12/20/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 9/18/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/18/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/18/2024 LEE GUILBEAUX
Tract Map conditions Cleared 9/20/2024 ALEX VELA
Eng Process Fee Ord 176,300 Cleared 10/3/2024 BIAINA HARITUNIAN
Sewer availability Cleared 10/3/2024 BIAINA HARITUNIAN

Contact Information

Contractor Chief Top Remodeling Inc; Lic. No.: 1096793-B 240 N CRESCENT DR #304      BEVERLY HILLS, CA 90210
Engineer Valencia,, Byron Steve; Lic. No.: C87372 16000 VENTURA BLVD., PH 1203      ENCINO, CA 91436

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/25/2024 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 12/4/2024 Not Ready for Inspection DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 12/31/2024 Corrections Issued DAVID SCANTLIN
Special/Order Compliance 1/21/2025 Partial Inspection JUAN ALVARADO
Footing/Foundation/Slab 1/27/2025 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 2/12/2025 Partial Approval KRISTEN CAUSEY
ELECTRICAL-Rough 5/30/2025 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 6/17/2025 Conditional Approval KRISTEN CAUSEY
ELECTRICAL-Rough 6/17/2025 Approved KRISTEN CAUSEY
Green Building Rough 6/17/2025 Approved KRISTEN CAUSEY
HVAC-Rough 6/17/2025 Approved KRISTEN CAUSEY
PLUMBING-Rough 6/17/2025 Approved KRISTEN CAUSEY
Insulation 7/3/2025 Partial Approval DAVID SCANTLIN
Insulation 7/14/2025 Approved DAVID SCANTLIN
Shower Pan 7/14/2025 Approved DAVID SCANTLIN
Drywall Nailing 7/21/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 10/23/2025 Approved KRISTEN CAUSEY
Final 10/23/2025 Corrections Issued KRISTEN CAUSEY
Green Building Final 10/23/2025 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 10/23/2025 SGSOV Approved KRISTEN CAUSEY
Service/Power Release 10/23/2025 Not Ready for Inspection KRISTEN CAUSEY
Smoke Detectors 10/23/2025 Approved KRISTEN CAUSEY
Final 11/4/2025 Not Ready for Inspection DAVID SCANTLIN
Service/Power Release 11/4/2025 Not Ready for Inspection DAVID SCANTLIN
Final 12/4/2025 Not Ready for Inspection DAVID SCANTLIN
Service/Power Release 12/4/2025 Not Ready for Inspection DAVID SCANTLIN
Final 12/17/2025 OK to Issue CofO DAVID SCANTLIN
Service/Power Release 12/17/2025 Approved DAVID SCANTLIN