10526 N HILLHAVEN AVE 91042
Certificate Information: 10526 N HILLHAVEN AVE 91042
- Application / Permit
- 24010-20000-03806
- Plan Check / Job No.
- B24VN13992
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW 29'-4" X 31'-10" DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g). NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 2/4/2025
- Issuing Office
- Current Status
- CofO Issued on 1/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2024 | RAPHAEL ROSAS |
| Corrections Issued | 9/11/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 9/12/2024 | STEVEN KIM |
| Applicant returned to address corrections | 1/21/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 1/24/2025 | RAPHAEL ROSAS |
| Issued | 2/4/2025 | APPLICANT |
| CofO in Progress | 12/12/2025 | MATTHEW NELSON |
| Permit Finaled | 1/13/2026 | RUBEN SALAS |
| CofO Issued | 1/13/2026 | RUBEN SALAS |
| Permit Finaled | 1/13/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/13/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 9/13/2024 | CARLOS AGUILERA |
| ZA Case | Cleared | 9/18/2024 | DORIAN AGUILAR |
| Private sewage disp. approval | Cleared | 9/25/2024 | DAN RYAN EVANGELISTA |
| Hydrant and Access approval | Cleared | 12/5/2024 | JERRY KAO |
| GPI Written Notices | Cleared | 1/21/2025 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 1/21/2025 | RAPHAEL ROSAS |
Contact Information
| Contractor | Melkonyan Artsvik; Lic. No.: 1016658-B | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/28/2025 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 4/11/2025 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 4/18/2025 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2025 | Approved | WILLIAM WREN |
| HVAC-Rough | 5/22/2025 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 5/22/2025 | Corrections Issued | WILLIAM WREN |
| ELECTRICAL-Rough | 5/29/2025 | Corrections Issued | JUAN VALENZUELA |
| Interior/Exterior Lathing | 5/29/2025 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 5/29/2025 | Approved | JUAN VALENZUELA |
| Wood Frame | 5/29/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/5/2025 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 6/5/2025 | Approved | WILLIAM WREN |
| Green Building Rough | 6/5/2025 | Approved | WILLIAM WREN |
| Verify Sprinkler Sign Off | 6/5/2025 | Approved | WILLIAM WREN |
| Insulation | 6/10/2025 | Corrections Issued | DAVID ANDERSON |
| Insulation | 6/12/2025 | Approved | WILLIAM WREN |
| Drywall Nailing | 6/16/2025 | Partial Approval | WILLIAM WREN |
| Interior/Exterior Lathing | 7/1/2025 | Approved | WILLIAM WREN |
| Shower Pan | 7/1/2025 | Approved | WILLIAM WREN |
| Sewer | 7/15/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 10/1/2025 | Approved | WILLIAM WREN |
| Final | 10/1/2025 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 10/1/2025 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 10/1/2025 | SGSOV Not Required | WILLIAM WREN |
| Service/Power Release | 10/1/2025 | Approved | WILLIAM WREN |
| Smoke Detectors | 10/1/2025 | Approved | WILLIAM WREN |
| Final | 10/6/2025 | Partial Approval | KEVIN BERBERYAN |
| Special/Order Compliance | 10/8/2025 | Corrections Issued | KEVIN BERBERYAN |
| Final | 12/12/2025 | OK to Issue CofO | MATTHEW NELSON |