10526 N HILLHAVEN AVE 91042

Certificate Information: 10526 N HILLHAVEN AVE 91042

Application / Permit
24010-20000-03806
Plan Check / Job No.
B24VN13992
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW 29'-4" X 31'-10" DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g). NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 2/4/2025
Issuing Office
Current Status
CofO Issued on 1/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2024 APPLICANT
Assigned to Plan Check Engineer 9/5/2024 RAPHAEL ROSAS
Corrections Issued 9/11/2024 RAPHAEL ROSAS
Quality Review Completed 9/12/2024 STEVEN KIM
Applicant returned to address corrections 1/21/2025 RAPHAEL ROSAS
Plan Check Approved 1/24/2025 RAPHAEL ROSAS
Issued 2/4/2025 APPLICANT
CofO in Progress 12/12/2025 MATTHEW NELSON
Permit Finaled 1/13/2026 RUBEN SALAS
CofO Issued 1/13/2026 RUBEN SALAS
Permit Finaled 1/13/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/13/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/13/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 9/13/2024 CARLOS AGUILERA
ZA Case Cleared 9/18/2024 DORIAN AGUILAR
Private sewage disp. approval Cleared 9/25/2024 DAN RYAN EVANGELISTA
Hydrant and Access approval Cleared 12/5/2024 JERRY KAO
GPI Written Notices Cleared 1/21/2025 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 1/21/2025 RAPHAEL ROSAS

Contact Information

Contractor Melkonyan Artsvik; Lic. No.: 1016658-B       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/28/2025 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 4/11/2025 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 4/18/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Approved WILLIAM WREN
HVAC-Rough 5/22/2025 Approved WILLIAM WREN
PLUMBING-Rough 5/22/2025 Corrections Issued WILLIAM WREN
ELECTRICAL-Rough 5/29/2025 Corrections Issued JUAN VALENZUELA
Interior/Exterior Lathing 5/29/2025 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 5/29/2025 Approved JUAN VALENZUELA
Wood Frame 5/29/2025 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 6/5/2025 Approved WILLIAM WREN
ELECTRICAL-Rough 6/5/2025 Approved WILLIAM WREN
Green Building Rough 6/5/2025 Approved WILLIAM WREN
Verify Sprinkler Sign Off 6/5/2025 Approved WILLIAM WREN
Insulation 6/10/2025 Corrections Issued DAVID ANDERSON
Insulation 6/12/2025 Approved WILLIAM WREN
Drywall Nailing 6/16/2025 Partial Approval WILLIAM WREN
Interior/Exterior Lathing 7/1/2025 Approved WILLIAM WREN
Shower Pan 7/1/2025 Approved WILLIAM WREN
Sewer 7/15/2025 Approved LOUIS ESCOTO
Drywall Nailing 10/1/2025 Approved WILLIAM WREN
Final 10/1/2025 Corrections Issued WILLIAM WREN
Green Building Final 10/1/2025 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 10/1/2025 SGSOV Not Required WILLIAM WREN
Service/Power Release 10/1/2025 Approved WILLIAM WREN
Smoke Detectors 10/1/2025 Approved WILLIAM WREN
Final 10/6/2025 Partial Approval KEVIN BERBERYAN
Special/Order Compliance 10/8/2025 Corrections Issued KEVIN BERBERYAN
Final 12/12/2025 OK to Issue CofO MATTHEW NELSON