20403 W RUSTON ROAD 91364

Certificate Information: 20403 W RUSTON ROAD 91364

Application / Permit
24010-20000-03786
Plan Check / Job No.
B24VN15794
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30' X 46' ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d); EQUIPPED WITH NPFA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 1/27/2025
Issuing Office
Valley
Current Status
Issued on 1/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/6/2024 APPLICANT
Assigned to Plan Check Engineer 9/19/2024 SELLA BENYAMIN
Corrections Issued 9/26/2024 SELLA BENYAMIN
Quality Review Completed 10/4/2024 STEVEN KIM
Building Plans Picked Up 10/8/2024 APPLICANT
Applicant returned to address corrections 1/3/2025 SELLA BENYAMIN
Plan Check Approved 1/14/2025 SELLA BENYAMIN
Issued 1/27/2025 APPLICANT

Permit Application Clearance Information

Street Frontage Cleared 10/21/2024 CARLOS RAMIREZ
Address approval Cleared 11/5/2024 CARLOS RAMIREZ
BHO/Hillside ordinance Cleared 11/5/2024 CARLOS RAMIREZ
BHO/Hillside ordinance Cleared 11/5/2024 CARLOS RAMIREZ
BHO/Hillside ordinance Cleared 11/5/2024 CARLOS RAMIREZ
BHO/Hillside ordinance Cleared 11/5/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 11/5/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 11/12/2024 CARLOS RAMIREZ
Sewer availability Cleared 11/14/2024 CARLOS RAMIREZ
Hydrant and Access approval Cleared 1/6/2025 KENNETH FRASER
Hold Cleared 2/10/2025 SANDRA SOH

Contact Information

Contractor Ag Construction And Management Inc; Lic. No.: 1113828-B 20238 LANARK ST      WINNETKA, CA 91606
Engineer Mercado,, Lizandro; Lic. No.: S4331 27240 TURNBERRY LN STE 200      VALENCIA, CA 91355

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2025 Corrections Issued JOHN HAYES
Pre-Inspection 2/18/2025 Not Ready for Inspection JOHN HAYES
Deputy Other (see comments) 2/19/2025 Partial Approval SEAN WIRCH
Piling/Pier/Caisson 2/21/2025 Partial Approval JOHN HAYES
Deputy Other (see comments) 2/24/2025 Conditional Approval JOHN HAYES
Deputy Reinf. Concrete 2/26/2025 Partial Approval SEAN WIRCH
Deputy Reinf. Concrete 3/25/2025 Partial Approval SEAN WIRCH
Footing/Foundation/Slab 3/25/2025 Not Ready for Inspection JOHN COLEMAN
Footing/Foundation/Slab 3/28/2025 Partial Approval JOHN COLEMAN
Deputy Reinf. Concrete 4/2/2025 Conditional Approval JOHN HAYES
Sewer 4/11/2025 Not Ready for Inspection SEAN WIRCH
Underground Mechanical 4/11/2025 Partial Approval SEAN WIRCH
Footing/Foundation/Slab 4/18/2025 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 7/16/2025 Partial Approval SCOTT SOBEL
HVAC-Rough 7/16/2025 Corrections Issued SCOTT SOBEL
Shower Pan 7/16/2025 Corrections Issued SCOTT SOBEL
Interior/Exterior Lathing 8/22/2025 Partial Approval JOHN HAYES
Shower Pan 8/22/2025 Partial Approval JOHN HAYES
Interior/Exterior Lathing 9/29/2025 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 10/30/2025 Approved JOHN HAYES
Green Building Rough 10/30/2025 Approved JOHN HAYES
HVAC-Rough 10/30/2025 Partial Approval JOHN HAYES
Rough-Elec/Plmb/HVAC 10/30/2025 Approved JOHN HAYES
Shower Pan 10/30/2025 Approved JOHN HAYES
Verify Sprinkler Sign Off 10/30/2025 Approved JOHN HAYES
HVAC-Rough 11/12/2025 Approved JOHN HAYES
Insulation 11/12/2025 Approved JOHN HAYES
Drywall Nailing 11/18/2025 Approved HENRY KIM
HVAC-Final 11/18/2025 Corrections Issued HENRY KIM