4619 N ATOLL AVE 91423

Certificate Information: 4619 N ATOLL AVE 91423

Application / Permit
24010-20000-03741
Plan Check / Job No.
B24VN15510
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 14'-0" x 32'-0" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)-(d) PER ENGINEERING
Permit Issued
Issued on 2/19/2025
Issuing Office
Valley
Current Status
CofO Issued on 3/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/5/2024 APPLICANT
Assigned to Plan Check Engineer 9/5/2024 ALFRED RAMIREZ
Corrections Issued 9/8/2024 ALFRED RAMIREZ
Quality Review Completed 9/12/2024 STEVEN KIM
Building Plans Picked Up 9/13/2024 APPLICANT
Applicant returned to address corrections 2/18/2025 ALFRED RAMIREZ
Plan Check Approved 2/19/2025 ALFRED RAMIREZ
Issued 2/19/2025 APPLICANT
CofO in Progress 1/15/2026 CHRISTOPHE COCHRAN
Permit Finaled 3/10/2026 RUBEN SALAS
CofO Issued 3/10/2026 RUBEN SALAS
Permit Finaled 3/10/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/24/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/25/2024 BIAINA HARITUNIAN
Construction within easement Cleared 11/6/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 1/15/2025 SARAH YOUSSEF
Sewer availability Cleared 1/25/2025 BIAINA HARITUNIAN
ZI Cleared 1/27/2025 BRENNEN OBETO
Roof/Waste drainage to street Cleared 2/18/2025 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/3/2025 Approved CHRISTOPHE COCHRAN
Underground Mechanical 4/3/2025 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 4/17/2025 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 4/17/2025 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2025 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 7/1/2025 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 7/1/2025 Approved CHRISTOPHE COCHRAN
Underground Mechanical 7/17/2025 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 7/22/2025 Approved CHRISTOPHE COCHRAN
HVAC-Rough 7/22/2025 Approved CHRISTOPHE COCHRAN
Deputy Wood Construction 7/31/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 8/1/2025 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 8/1/2025 Approved CHRISTOPHE COCHRAN
Green Building Rough 8/1/2025 Approved CHRISTOPHE COCHRAN
MERV13>=Rough 8/1/2025 Approved CHRISTOPHE COCHRAN
Shower Pan 8/1/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 8/1/2025 Approved CHRISTOPHE COCHRAN
Shower Pan 8/6/2025 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/15/2025 Approved CHRISTOPHE COCHRAN
Insulation 8/21/2025 Approved CHRISTOPHE COCHRAN
Drywall Nailing 8/26/2025 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/26/2025 Approved CHRISTOPHE COCHRAN
Final 12/19/2025 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/19/2025 SGSOV Not Ready JAVIER RAMOS JR
Final 1/12/2026 Partial Inspection CHRISTOPHE COCHRAN
Green Building Final 1/12/2026 Approved CHRISTOPHE COCHRAN
MERV13>=Final 1/12/2026 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 1/12/2026 SGSOV Not Required CHRISTOPHE COCHRAN
Service/Power Release 1/12/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 1/12/2026 Approved CHRISTOPHE COCHRAN
Final 1/15/2026 OK to Issue CofO CHRISTOPHE COCHRAN
Service/Power Release 1/15/2026 Approved CHRISTOPHE COCHRAN