6055 N MELVIN AVE 91356
Certificate Information: 6055 N MELVIN AVE 91356
- Application / Permit
- 24010-20000-03714
- Plan Check / Job No.
- B24VN12828
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 11'-6" X 22' DETACHED PATIO COVER.
- Permit Issued
- Issued on 2/19/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/5/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2024 | RAPHAEL ROSAS |
| Corrections Issued | 9/6/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 9/11/2024 | STEVEN KIM |
| Applicant returned to address corrections | 11/5/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/4/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 2/5/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 2/18/2025 | RAPHAEL ROSAS |
| No Progress | 2/19/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 2/19/2025 | RAPHAEL ROSAS |
| Issued | 2/19/2025 | APPLICANT |
| CofO in Progress | 5/5/2026 | JON MCHUGH |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 9/18/2024 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2025 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 1/31/2025 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 2/3/2025 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/11/2025 | Conditional Approval | JON MCHUGH |
| Deputy Reinf. Concrete | 3/11/2025 | Conditional Approval | JON MCHUGH |
| Piling/Pier/Caisson | 3/11/2025 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 3/12/2025 | Approved | JON MCHUGH |
| Special/Order Compliance | 3/12/2025 | Corrections Issued | JON MCHUGH |
| Deputy Reinf. Concrete | 3/20/2025 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 5/5/2025 | Approved | JON MCHUGH |
| HVAC-Rough | 5/16/2025 | Approved | JON MCHUGH |
| PLUMBING-Rough | 6/10/2025 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 6/16/2025 | Approved | JON MCHUGH |
| Green Building Rough | 6/16/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 6/16/2025 | Partial Approval | JON MCHUGH |
| Verify Sprinkler Sign Off | 6/16/2025 | Approved | JON MCHUGH |
| Insulation | 6/26/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 6/26/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 4/21/2026 | Approved | JON MCHUGH |
| Final | 4/21/2026 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 4/21/2026 | Approved | JON MCHUGH |
| Green Building Final | 4/21/2026 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 4/21/2026 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 4/21/2026 | Not Required | JON MCHUGH |
| Smoke Detectors | 4/21/2026 | Approved | JON MCHUGH |
| Final | 5/5/2026 | OK to Issue CofO | JON MCHUGH |