6057 N MELVIN AVE 91356
Certificate Information: 6057 N MELVIN AVE 91356
- Application / Permit
- 24010-20000-03713
- Plan Check / Job No.
- B24VN12828
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 31'-2" X 34' 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g). NFPA 13R FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/19/2025
- Issuing Office
- Current Status
- CofO in Progress on 4/20/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2024 | RAPHAEL ROSAS |
| Corrections Issued | 9/6/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 9/11/2024 | STEVEN KIM |
| Applicant returned to address corrections | 11/5/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/4/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 2/5/2025 | RAPHAEL ROSAS |
| Issued | 2/19/2025 | APPLICANT |
| CofO in Progress | 4/20/2026 | JON MCHUGH |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/6/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 9/18/2024 | MARTIN FRAGOSO |
| Address approval | Cleared | 10/1/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 10/1/2024 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 1/29/2025 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/7/2025 | Partial Approval | JON MCHUGH |
| Sewer | 3/7/2025 | Approved | JON MCHUGH |
| Deputy Reinf. Concrete | 3/11/2025 | Conditional Approval | JON MCHUGH |
| Footing/Foundation/Slab | 3/13/2025 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 5/5/2025 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 5/13/2025 | Approved | JON MCHUGH |
| HVAC-Rough | 5/16/2025 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 5/28/2025 | Partial Approval | JON MCHUGH |
| HVAC-Rough | 6/10/2025 | Approved | JON MCHUGH |
| PLUMBING-Rough | 6/10/2025 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 6/16/2025 | Approved | JON MCHUGH |
| Green Building Rough | 6/16/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 6/16/2025 | Partial Approval | JON MCHUGH |
| Verify Sprinkler Sign Off | 6/16/2025 | Approved | JON MCHUGH |
| Insulation | 6/26/2025 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 6/26/2025 | Approved | JON MCHUGH |
| Drywall Nailing | 7/10/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 2/24/2026 | No Access for Inspection | MORRIS JACKSON |
| ELECTRICAL-Final | 3/6/2026 | Partial Approval | JON MCHUGH |
| PLUMBING-Final | 3/6/2026 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 3/10/2026 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 3/10/2026 | Approved | JON MCHUGH |
| PLUMBING-Final | 3/10/2026 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 3/13/2026 | Approved | JON MCHUGH |
| Pre-Inspection | 4/2/2026 | Partial Inspection | JON MCHUGH |
| Final | 4/7/2026 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 4/7/2026 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 4/7/2026 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 4/7/2026 | Approved | JON MCHUGH |
| Final | 4/20/2026 | OK to Issue CofO | JON MCHUGH |