12775 1/2 W SUNBURST ST 91331
Certificate Information: 12775 1/2 W SUNBURST ST 91331
- Application / Permit
- 24010-20000-03710
- Plan Check / Job No.
- B24VN15271
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER CITY ORDINANCE
- Permit Issued
- Issued on 7/31/2025
- Issuing Office
- Current Status
- CofO Issued on 6/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2024 | JOSE VELAZQUEZ |
| Corrections Issued | 9/10/2024 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 4/7/2025 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 7/11/2025 | NAREG ATARIAN |
| Plan Check Approved | 7/18/2025 | NGHI SU |
| Issued | 7/31/2025 | APPLICANT |
| CofO in Progress | 5/20/2026 | MICHEL ABAJAN |
| Permit Finaled | 6/8/2026 | RUBEN SALAS |
| Permit Finaled | 6/8/2026 | RUBEN SALAS |
| CofO Issued | 6/8/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/31/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/31/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/4/2024 | CARLOS AGUILERA |
| CPC | Cleared | 5/6/2025 | JASON CHAN |
| Clean Up Green Up | Cleared | 5/6/2025 | JASON CHAN |
| ZA Case | Cleared | 5/6/2025 | JASON CHAN |
| Hold | Cleared | 9/2/2025 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chen,, Min Dar; Lic. No.: NA40168 | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/12/2025 | Approved | MICHEL ABAJAN |
| Gas Test | 11/12/2025 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 11/12/2025 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 11/12/2025 | Approved | MICHEL ABAJAN |
| Sewer | 11/12/2025 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 11/12/2025 | Approved | MICHEL ABAJAN |
| Deputy Reinf. Concrete | 12/2/2025 | Conditional Approval | RAUL OLAGI |
| PLUMBING-Rough | 12/2/2025 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/19/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/19/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 12/19/2025 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 12/19/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/19/2025 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 12/19/2025 | Approved | MICHEL ABAJAN |
| Insulation | 12/26/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/26/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 12/30/2025 | Approved | LOUIS ESCOTO |
| ELECTRICAL-Final | 2/24/2026 | Approved | MICHEL ABAJAN |
| Final | 2/24/2026 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 2/24/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 2/24/2026 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 2/24/2026 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 2/24/2026 | Approved | MICHEL ABAJAN |
| Final | 5/19/2026 | OK to Issue CofO | MICHEL ABAJAN |