10939 N NASSAU AVE 91040
Certificate Information: 10939 N NASSAU AVE 91040
- Application / Permit
- 24010-20000-03709
- Plan Check / Job No.
- B24VN15259
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 5/7/2025
- Issuing Office
- Current Status
- CofO Issued on 3/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2024 | DANIEL YIP |
| Corrections Issued | 9/15/2024 | DANIEL YIP |
| Quality Review Completed | 9/19/2024 | GARO TELMI |
| Applicant returned to address corrections | 11/5/2024 | DANIEL YIP |
| Plan Check Approved | 5/6/2025 | DANIEL YIP |
| Issued | 5/7/2025 | APPLICANT |
| CofO in Progress | 3/3/2026 | NICHOLAS TROWBRIDGE |
| CofO Issued | 3/26/2026 | RUBEN SALAS |
| Permit Finaled | 3/26/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/16/2024 | DANIEL YIP |
| Address approval | Cleared | 10/11/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 10/11/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 10/16/2024 | RYAN CASTRO |
| Construction near power lines | Cleared | 4/22/2025 | GEVORK KARAPETYAN |
| GPI Written Notices | Cleared | 5/6/2025 | DANIEL YIP |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 6/24/2025 | Approved | WILLIAM WREN |
| Underground Mechanical | 6/25/2025 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 7/22/2025 | Partial Approval | WILLIAM WREN |
| Sewer | 7/22/2025 | Approved | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 8/6/2025 | Partial Approval | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 8/22/2025 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2025 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 10/2/2025 | Not Ready for Inspection | WILLIAM WREN |
| Verify Sprinkler Sign Off | 10/2/2025 | Not Ready for Inspection | WILLIAM WREN |
| Wood Frame | 10/2/2025 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 11/4/2025 | Approved | DAVID MATSON |
| Rough-Elec/Plmb/HVAC | 11/4/2025 | Corrections Issued | DAVID MATSON |
| BUILDING-Rough-Frame | 11/12/2025 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 11/12/2025 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2025 | Approved | MATTHEW NELSON |
| Green Building Rough | 11/12/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 11/12/2025 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 11/12/2025 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/19/2025 | Partial Approval | KEVIN BERBERYAN |
| Insulation | 11/25/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 11/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 11/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 12/5/2025 | Approved | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 2/23/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 2/23/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 2/23/2026 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Final | 2/23/2026 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 2/23/2026 | SGSOV Not Required | NICHOLAS TROWBRIDGE |
| Service/Power Release | 2/23/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 2/23/2026 | Approved | NICHOLAS TROWBRIDGE |
| Final | 3/2/2026 | OK to Issue CofO | NICHOLAS TROWBRIDGE |
| Service/Power Release | 3/2/2026 | Approved | NICHOLAS TROWBRIDGE |